Environmental Monitoring Report Date: February 2014 Reporting Period of July-December 2013 № 2629-UZB и № 2630-UZB: Talimarjan Clean Power Project. Prepared by PMU «Talimarjan ТPР» for the Asian Development Bank. 1 ABBREVIATIONS TPP – Talimarjan Power Plant CCGT – Combined Cycle Gas Turbine PMU - Project Management Unit SPS – Safeguards policy statement EIA - Environmental impact assessment NPC - Nature Protection Committee EMP - Environmental Management Plan SEMP - Site Environmental Management Plan NES - National environmental specialist IES - International environmental specialist CDM - Clean Development Mechanism KMK - Karshi Main Canal PDD - Project design document UNFCCC - Framework Convention on Climate Change of the United Nations CSMM - Corporate Solutions и Mott MacDonald Team HDEC - Hyundai Engineering and Construction and Daewoo International Consortium HSE plan - Health, Safety and Environmental Plan WEIGHTS AND MEASURES MW – Megawatt km – Kilometer °C – Celsius degree 2 GLOSSARY I Section. II Section. Introduction………………..………………………………. 5 1.1 General information on environment protection………. 5 1.2 Description of the construction works under the project… 8 1.3 Changes in the organization or composition of the Environment Department …………………………………… 9 Environmental Management ………………………………… 11 2.1 Status of Environmental Management ………………….. 11 2.2 Ecological monitoring..…………………………….…….. 11 Appendix 1. Decree Cabinet of Ministry of Republic of Uzbekistan № 491 «On government ecological expertise»…………….. Appendix 2. The environmental clearance from Nature Protection Committee…………………………………………………... Appendix 3. Results of environmental inspection (report prepared by the Supervision consultant of Corporate Solutions и Mott MacDonald, November 2013)…………………..…………….. Appendix 4. Report on environmental audit (report prepared by LLC «Nazar Business Technology», January 2014)…….……….. Appendix 5. Health, Safety and Environmental Management (Chapter from monthly progress report of «Hyundai Engineering and Construction and Daewoo International Consortium», December 2013)…..…………................................................. Appendix 6. Environmental management plan while implementation the project (prepared by «Hyundai Engineering and Construction and Daewoo International Consortium», January 2014г.)………………………………………………………… 3 NOTE In this report, "$" refers to US dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Company authorized representative I certify that the data contained in this report completely and accurately represents operations during this reporting period: Signature: Yuliya Yakubova Title: Environment Specialist of PMU “Talimarjan TPP” Date: February 2014 Contact Details: Telephone: (+998 71) 233-24-30 Mobile: (+998 93) 530-46-21 E-mail: grp_tal_tes@mail.ru , yulia.kakan@yandex.ru 4 1. INTRODUCTION The project is implemented in accordance with the Decree of the President of the Republic of Uzbekistan dated 7 March 2013 No.ПП-1933 "On the measures to ensure the implementation of the investment project “Expansion of Talimarjan TPP with the construction of two CCGT with a capacity of 450 MW". The site is an existing gas fired power plant, which currently generates 800 megawatts (MW). The project will install two additional combined cycle gas turbine (CCGT) units of about 450 MW each at the site. Based on ADB's safeguards policy statement (SPS), the Project is classified as follows: (i) environment (category A) – environmental impact assessment (EIA), (ii) involuntary resettlement (category C) – no actions, and (iii) indigenous peoples (category C) – no actions. Therefore, an environmental clearance from ADB was obtained in December 2009. According of Decree Cabinet of Ministry of Republic of Uzbekistan № 491 «On government ecological expertise» the Project is classified as a class 1 Project (is attached in appendix 1) Under the Uzbekistan Environmental Legislation. The environmental clearance was obtained from Nature Protection Committee (NPC) on 5 October 2009. According to the legislation of the Republic of Uzbekistan the correction is made after 3 years, a new Conclusion of Ecological Expertise № 18/768 dated 13 August 2013 is received (attached in appendix 2). The objective of this report is to provide a progress in implementing Environmental Management Plan and Environmental Monitoring Plan (EMP) as stated in the Environmental impact. This Report was prepared to cover the period of July - December 2013. 1.1. OVERALL ENVIRONMENTAL INFORMATION Yes Is the project materially compliant with all relevant No ADB Requirements Is the project materially compliant with all Yes 5 applicable environmental and social laws and regulations? No Have there been any Yes accidents or incidents that No have caused damage to the environment, brought about injuries or fatalities, affected project labour or local communities, affected cultural property, or created liabilities for the company? Have there been any changes to environment, social, labour or health and safety laws or regulations that have materially affected the company? Yes No How many inspections did you receive from environmental specialists of the PMU during the reporting period? 1 On 19 November 2013 the Monitoring of compliance with environmental measures has been conducted at the construction site of CCGT by Yuliya Yakubova, PMU Safeguard Specialist. Visual inspection on the main environmental indicators is conducted. Violations of environmental legislation and safety regulations are not revealed. Construction works are in compliance with the Environmental Management Plan. How many inspections have been conducted by the Supervision Consultant during the 3 Natasha Sim, Supervision Consultant has visited the construction site on the 17, 18, 25 October 2013; on the 6, 7 November 2013; 6 reporting period? on and on the 10 December 2013. Based on the results of the conducted inspections, the Consultant provides PMU with monitoring reports. These reports for the period October -November 2013 are presented in Appendix 3. How many inspections have been conducted by local ecological bodies during the reporting period? 0 Due to the fact that the Talimarjan TPP is restricted access enterprise, the Karshi Regional Committee for the Nature Protection conducts the coordination inspection 1 time every 3 years; the next inspection will take place in spring of 2014. How many inspections have been conducted by other organizations during the reporting period? 1 On 1 November 2013 the environmental audit has been conducted by LLC «Nazar Business Technology». The results of conducted audit are presented in Appendix 4. Have these visits resulted in any penalties, fines and/or corrective action plans? Yes No Has the Company engaged Yes any contractors for No project-related work in the reporting period? Contract Agreement No.SJSC/UzbekEnergo/ICB-2010-001 dated 07 March 2013 between the UE "Talimarjan TPP", SJSC "Uzbekenergo" and the Consortium of the foreign companies «Hyundai Engineering and Construction and Daewoo International Consortium» for the “turnkey” construction of two combinedcycle plants with a capacity of 450 MW is signed. Since 10.10.2013 the Contractor's representative Mr. Jeong Hyeon Kim works 7 at the construction site, who provides active support and regular inspections on HSE in accordance with the Environmental Management Plan. Were any of the violations Yes stated above the No responsibility of contractors? Have any operations been reduced, temporarily suspended or closed down due to environmental, health, safety or labour reasons? Only minor violations as discussed in the Consultant's reports in Appendix 3. Yes No Environment initiatives or sub-projects undertaking during the reporting period to improve the company’s environmental performance and/or management systems: ADB has employed LLC «Nazar Business Technology» as a consultant for training on compliance with ADB’s requirements on the environmental protection and analysis of implementation of ecological policy in Uzbekistan. This training was held on 22-23August 2013 in Tashkent and the Project Management Unit experts, Talimarjan TPP Ecologist and representatives of Hyundai-contractor under the project have participated. On 27 October, 2013 experts of LLC «Nazar Business Technology» have conducted the audit of all environmental documents available in the office of the PMU in Tashkent, and on 1 November 2013 the environmental audit has been conducted at the construction site. 1.2. DESCRIPTION OF CONSTRUCTION WORK During the period under review, the project is at the stage of construction works. According to the report on project implementation for December 2013, submitted by Hyundai Engineering and Construction and Daewoo International Consortium (HDEC), as of 31 December 2013, the progress of project is 10,25%. 8 Figure 1: Project Overall S-Curve (taken from the HDEC Monthly Progress Report December 2013) 1.3. ORGANIZATION OF ENVIRONMENTAL WORK There are no changes in the composition of the Environment Department. PMU Environment Specialist - Yuliya Yakubova Station Ecologist - Nizom Rakhimov Since 1 July 2013 the International Environmental Specialist of "Corporate Solutions Consulting Limited" Natasha Sim has commenced the work. Also from the party of Corporate Solutions and Mott MacDonald Team (CSMM) the local consultant on Social, Gender and Environmental issues Lyudmila Khegay is involved. Since 10 October 2013 the Contractor's representative Mr. Jeong Hyeon Kim works at the construction site, who provides active support and regular inspections on HSE in accordance with the Environmental Management Plan, as well as his assistant Khusan Khidirov, Environmental and Safety Specialist. 9 ADB Ms. Dewi Utami PMU Yuliya Yakubova CSMM Natasha Sim Hundai Mr. Jeong Hyeon Kim CSMM Lyudmila Khegay Hundai Khusan Khidirov Talimarjan TPP Nizom Rakhimov Regarding environmental works: The Contractor shall (a) establish an operational system for managing environmental impacts, (b) carry out all of the monitoring and mitigation measures set out in the Environmental Management Plan (EMP), and to prepare Environmental Action Plan (EAP). The Contractor shall submit to the Employer monthly reports on the carrying out of such measures. Currently HDEC provides the PMU with monthly progress reports, which includes a chapter "HSE Management" (Appendix 5), as well as separate monthly HSE reports. The Consultant also provides the PMU with a quarterly report, that includes a section on HSE, the report on monitoring the implementation of the Environment Work Plan after visiting the construction site, as well as a separate semi-annual report on the results of an environmental inspection. The PMU reviews and analyzes all of these reports and takes corrective measures if necessary. According to the results of joint activities Contractor - Consultant PMU the semi-annual HSE reports for the ADB are created. Also according to the ADB policy, the PMU sends the semi-annual HSE reports to the Karshi Regional Committee for the Nature Protection for reference. 10 II. ENVIRONMENTAL MANAGEMENT PLAN (EMP) 2. 1 STATUS OF ENVIRONMENTAL MANAGEMENT PLAN. In September 2013, HDEC has provided the HSE plan, which includes the Site Environmental Management Plan (SEMP) and Environmental Management Plan. This plan has been reviewed by the PMU and the Consultant and sent to the Contractor for updating. When updating the HSE plan the Contractor was recommended to base plans on the Environmental Impact Assessment (2009), Environmental Action Plan (2009). This plan was updated twice and the final third version of the EMP was acceptable to PMU and Consultant and was submitted in January 2014. The agreed plan is convenient for the ongoing project and guarantees minimum negative impacts on the environment (the EMP can be found in Appendix 6). The EMP will be implemented by the Contractor and monitored by SJSC “Uzbekenergo” and the Consultant. 2. 2 ECOLOGICAL MONITORING. Based on the EIA, the PMU with the Station ecologist has carried out the Monitoring of compliance with the requirements of the Environmental Management Plan (EMP) at the construction site. The PMU monitoring was conducted one time in November 2013, but the station ecologist conducts a visual inspection of the construction site on a weekly basis. Chemical Analysis Laboratory of the station also carries out monthly analyzes of water samples from the Karshi Main Canal and sewage treatment plants. During the reporting period EMP violations were not revealed. Preparatory and construction works are carried out in accordance with all the requirements of the environmental legislation of the Republic of Uzbekistan. Monitoring of the implementation of the EMP on a regular basis is conducted by the Consultant. During the reporting period, the Consultant has conducted three environmental inspections (one per month). The results of inspections are presented in Appendix 3. 11 HDEC engineers conduct daily rounds and a daily survey of the construction site. Table 2.2.1 provides information on controlled aspects from the monthly HSE report of HDEC. Table 2.1.1: HDEC Environmental Monitoring Table Aspects to be monitored 1. No dumping of waste outside Project site or in canal Means of monitoring Observation 2. General site condition Observation and cleanliness Location Frequency Throughout Project site Daily Throughout Project site Weekly Risk Status Low Waste disposal company take outside everyday Low On Monday HSE team checks around of PJT Site 3. Covering of all trucks moving to and from site Observation 4. Registration papers and compliance certificate of construction vehicles with local Government Observation 12 At site exit point Daily Security check point Random checks Low All trucks were inspected by Site Supervisor and Security Low All equipments have registration paper and certification with local government 5. Conditions at temporary waste storage areas, including security at areas and separation of hazardous and non-hazardous waste Observation Waste storage areas Daily Project site Daily Low 6. Conditions at construction workforce toilets Observation 7. Evidence of marking of worksite boundaries Observation Project site Weekly PJT site has fence and signboard 8. Condition and effectiveness of erosion and sediment controls Observation Project site After rain Low 9. Dust generation during windy conditions Observation Temp. waste areas were checked by site supervisor, waste company and security, everyday Building in progress HSE team and Site supervisor has inspection after rain Exposed areas throughout Project site 13 During windy conditions Middle Water sprinkling 4 times in a day 10. Number and type of community complaints received Project site Review of Complaints Monthly Low No comments Instrumental measurements of noise levels are represented in Table 2.2.2. Table 2.2.2: Noise Level Measurements from HDEC Sound Level (dBA) Location Limits Test Date Remark 02.Jan.2014 08.Jan.2014 15.Jan.2014 22.Jan.2014 45.8 46.3 46.0 49.8 approve 57.4 59.1 67.2 65.3 approve 42.1 43.8 41.8 44.5 Batch plant 39.8 41.2 40.4 40.1 approve Camp area 47.2 53.6 54.8 53.7 approve Nuristan 53.4 61.2 56.7 57.7 approve Contractor Office Power Block Gate Cooling Tower Gate 85 dBA approve The Subcontractor also has concluded a contract with the company for waste disposal and carries out regular HSE trainings. They hold a weekly HSE meeting every Wednesday with the subcontractor to discuss findings from the daily site surveys. Monitoring shows that the environmental requirements at the stage of construction works are fulfilled satisfactorily. Due to the fact that in January 2014 the final version of the Environmental Management Plan (EMP) was agreed, the PMU hopes to receive more comprehensive HSE reports from the Contractor, covering all aspects of the EMP. During the reporting period there were no violations of environmental legislation and no complaints from the public. 14 Letterhead of the State Committee for Nature Protection of the Republic of Uzbekistan 13 August 2013 No. 18/768 CONCLUSION of Government Ecological Expertise Subject: Environmental impact assessment of the "Expansion of Talimarjan TPP with the construction of two CCGT with a capacity of 450 MW" project Employer: UE “Talimarjan TPP” Designer: OJSC “Teploelectroproect” Mr. NORMUMINOV A.A. Director of UE “Talimarjan TPP” cc: Mr. MAMANAZAROV M.KH. Chairman of Kashkadaryaoblkomprirody Ms.BAYMATOVA T.B. Technical director of OJSC “Teploelectroproect” Materials of the first stage of Environmental impact assessment of the "Expansion of Talimarjan TPP with the construction of two CCGT with a capacity of 450 MW" has been submitted for the Government Ecological Expertise. The enterprise is located at Nuristan settlement, Nishan area, Kashkadarya region in 18 km from the Nishan area center. The nearest residential buildings are in 700 m to the north-east from the enterprise, in 1.0 km from priority sources of pollutant emissions to atmosphere. To the east from TPP at a distance of 1.0 km there is the rail road Karshi-Termez-Dushanbe. The station is located on the right bank of the Karshi Main Kanal, which is connected with Talimarjan reservoir (in 7 km). Talimarjan TPP is focused on power generation; the installed capacity - 800 MW. The power generation in 2012 is amounted to 5516308.8 thousand kWh. Natural gas is used as a main and reserve fuel at TPP, gas flow rate in 2012 is 1 amounted to 1323074.4 knm³, at that, specific reference fuel consumption for electrical supply is determined in a value of 313.25 g/kWh, heat-167.99 kg/Gcal. At existing situation the process equipment of TPP is presented by one power unit comprising: - steam turbine К-800-20-5 with a capacity of 800 MW with generator ТВВ -800-2. - boiler ТG-805-С3 with steam producing capacity of 2650 ton per hour The structure of block station includes also a starting heating boiler house equipped by four boilers U-50-3.9-440GM with steam producing capacity of 50 ton per hour and two water-heating boilers PTVM-30 with heat producing capacity of 30 Gcal per hour. The industrial and agricultural enterprises of a southern part of the republic are experiencing a deficiency in the electric energy as at Talimarjan TPP with the designed capacity of 3200 MW there is only one power unit with a capacity of 800 MW and being the basic source of electricity generation, thermal power plant is not able to meet the needs of the served region. In pursuance of the Resolution of the President of the Republic of Uzbekistan #ПП-1933 dated 7 March 2013, Talimarjan TPP expansion project with the construction of two CCGT is developed with increasing its capacity to 1,700 MW. The structure of CCGT includes gas turbine unit with the electrical capacity of 314 MW, waste-heat steam boiler and steam-turbine condensing unit with the electrical capacity of 157.7 MW. Natural gas flow rate will make 1267.38 mln.nm³ per year (162.964 nm³/h). Emission of smoke gases from new units is provided through two individual pipes with a height of 85 m and diameter of 7.2 m. Management of CCGT is planned through an automated system that allows ensuring of the control of the process parameters and execution of tasks for regulation, alarm and blocking of fuel supply in a case of any violations of the production cycle. Accommodation of two projected CCGT is planned at the territory of existing TPP from the main building without additional land acquisition. For stabilization of natural gas supply with the required parameters of pressure (up to 39.5 bars) the construction of booster compressor station equipped with three gas compressor is planned. Water supply of CCGT is provided from existing networks of Talimarjan TPP (Karshi Main Canal) with consumption for technical needs, taking into 2 account the available capacities 591182 thousand m³/year. Water for the CCGT will be used in a cooling water system and chemical water treatment. Wastewater in the turbines under the straight-through arrangement is removed into the Karshi Main Canal below the water abstraction point. Losses replenishment in the process water circulation system is carried out by a fresh water supply from the additional water intake structures, located at the initial KMC area (from the Talimarjan reservoir). Considering a high mineralization, rigidity and turbidity of surface waters under the expansion of TPP the organization of additional (make-up) water pre-treatment with the arrangement of intake chamber and drilling waste disposal site is provided. For prevention of deposition and salts scaling formation as well as for disinfection the water is treated with the inhibitor and sodium hypochlorite. Number of wastewaters and sewage waters outlet in Karshi Main Canal remains unchanged: - Outlet No.1, through which the sanitary sewage is discharged after cleaning and drain of the water treatment plant in the manifold (collector) K-3-2 at a rate of 527.2 m3/h; - Outlet No.2, directing the partially clean waters of turbine condenser cooling system of power unit No.1 and two CCGT, as well as brine of distillation desalination plant in the discharge canal of KMC at a rate of 144243.5 m3/h. Analysis of the manufacturing parameters of installed equipment shows that at its design the requirements of water-saving technologies are taken into account: for comparison - the discharge of sewage waters from two combined cycle gas turbine will reach 45220 m/h while from the power unit No.1 - 93162 m/h. Thermal pollution of the Karshi Main Canal water as the result of partially clean waters discharge after coils cooling shall not exceed 3°C in the summer. The main source of sewage waters pollution with oil products is oil lubrication system of turbines. Oily sewage waters to be cleaned at the Integrated treatment of production waste waters. Under the expansion of thermal power plant to 1700 MW from 800 MW it is necessary to provide the reconstruction of facilities on the cleaning of oily sewage waters by adjusting the concentration of petroleum products to the background values that characterize the quality of water in Karshi Main Canal at the outlet from the Talimarjan reservoir. During the plant operation a carbon and nitrogen oxides, nitrogen and sulfur dioxides and benzo(a)pyrene get into the atmosphere currently, the bulk is accounted for the nitrogen dioxide - 2847.6 tons/year and nitrogen oxide - 441.3 3 tons/year. Gross emission of pollutants is 3289.4 tons/year. Flue gases from power unit are exhausted through a pipe with 270 m height and with a diameter of 6.6 m. Atmospheric air in this region is characterized by a moderate content of pollutants; Talimarjan TPP and motor transport brings the main contribution to the contamination of the atmosphere with nitrogen dioxide. With TPP emissions the nitrogen dioxide are generated outside of TPP reaching 0.19 of maximum permissible concentration (MPC) that is do not exceed the established limits (0.25 MPC). After the expansion of TPP at developing of its capacity to 1700 MW from 800 MW the pollutant emissions increase to 4431.29 tons/year (by 1141.89 tons/year), and the maximum concentrations of nitrogen dioxide, generating with TPP emissions outside of TPP will make 0.24 MPC (without taking into account a background) at the territory of Nuristan settlement 0.21 MPC. On other substances – they do not reach the values of 0.1 MPC. Specific emission rate of pollutants per unit of capacity (MW) are significantly reduced: from 4.11 tons till 2.6 tons. The generation of additional types of wastes during the construction of two CCGTs is not predicted, their quantity is increasing due to high consumption of lubricants, mercury-containing lamps, work clothing, etc., but standards of wastes generation will remain at the same level. For the purpose of noise reduction, CCGTs are equipped with acoustic enclosure, an Air Filtering and Conditioning System (AFCS) is installed, equipped with a filtration system and air heating that will provide effective cleaning of the air flowing to the suction pipe of CCGT. Environmental expertise of the submitted materials has shown their compliance with the requirements of the environmental laws on the scope and content of the first stage of the EIA and considers it necessary to develop the final stage - Statement of environmental effects (SEE) for the purpose of regulatory actions on emissions and discharges of pollutants into the environment, waste generation and emplacement of industrial waste separately by years in view of the commissioning schedule of CCGTs with a capacity of 450 MW. For the regulatory actions on discharges of pollutants to surface-stream flow under the SEE it is necessary to perform schemes of water disposal separately by discharges and the identifying the sources of pollutants supply in baseline characteristics. Prediction of water pollution of Karshi Main Canal with sewage 4 waters of TPP should be calculated depending on the mode of water flow in the canal. The draft of environmental impact statement of Talimarjan TPP expansion project with the construction of two CCGT with a capacity of 450 MW and increasing the plant capacity to 1700 MW is under the coordination of Government Ecological Expertise of the State Committee for Nature protection the Republic of Uzbekistan. Kashkadarya Regional Committee for Nature Protection should take under control the compliance with the requirements of environmental laws when placing the combined cycle gas turbines at the territory of Talimarjan TPP. Prior to the development and submission of the Statement of environmental effects by the Government Ecological Expertise it is necessary to submit to the State Committee for Nature protection the results of status monitoring of the Karshi Main Canal surface waters before and after discharge of Talimarjan TPP sewage waters. Deputy Chairman (signature) Action by: Ishmukhamedova T.R. Tel: 230-16-99 5 K. Sadykov Appendix N 1 Decree of Cabinet of Ministry of Republic of Uzbekistan. On Confirmation of Government Ecological Expertise in Republic of Uzbekistan In accordance with Action program for executing the of Decree of President of Republic of Uzbekistan dated 2 June of 2000 N UP – 2612 “Measures for implementing of Program of Liberalization and deepening of reforms in political, economic and spiritual areas of society and providing of the safety of country” and also for purposed of implementing the Law of Republic of Uzbekistan on “Ecological expertise” and implementing measures for development of legal-normative basis of providing of ecological safety Cabinet of Ministry approves: 1. To confirm: Regulation on government ecological expertise of Republic Uzbekistan accorind the appendix 1. List of activities according which is government ecological expertise is being carried out according the № 2. 2. Control for executing of this decree is on responsibility of deputy of Prime Minister of Republic of Uzbekistan T.H. Haltaeva. Prime- Minister of Republic of Uzbekistan U.Sultanov. Tashkent city 31 December 2001 № 491 Appendix N 2 To decree of Cabinet of Minister dated 31 December 2001 № 491 List Of Types of Activities for which is government ecological expertise is made on. Types of activities which at 1 category of influencing the environment (high risk) 1. Auto roads, subways railways, high speed roads and loading terminals of republican status. 2. Airports. 3. Base oil and oil products I category. 4. Reservoir with a capacity of over 200 million cubic meters. 5. Mining and processing plant capacity of over one million tons of ore per year. 6. Municipal waste landfills (for cities with populations of more than 200 thousand people.). 7. Hydroelectric power plants with a capacity of 30 MW. 8. Production of mining and mining-chemical raw materials to the volume of the rock mass production 2 million cubic meters. M / year or more, reclamation pits formed during extraction. 9. Extraction of fuel resources (oil, gas, coal, etc.). 10. Plants of ferrous and nonferrous metallurgy. 11. Leather-tanning business. 12. Sewage treatment plant capacity of more than 280 thousand cubic meters. m / day. 13. Power lines of republican status and national interstate status. 15. Machine-building Industry (Aircraft, Automotive, Tractor, motor building, etc.). 16. Designated storage or disposal of toxic wastes and tailings pond. 17. Incinerators. 18. Oil and gas pipelines of national importance. 19. Oil and gas refineries. 20. Dams. 21. Underground gas storage facilities. 22. Landfills leaching. 23. Enterprises using heap leach technology. 24. Enterprises Waste Processing I and II hazard classes. 26. Manufacture of accumulators, galvanic batteries and components. 27. The production of asbestos and asbestos products. 28. Manufacture of explosives. 29. Production of equipment or devices containing toxic substances regulated by international agreements. 30. Production, use and storage of radioactive materials (isotopes). 31. Manufacture of rubber and rubber products. 32. Production of glass containing toxic contaminants. 33. Manufacture of tobacco products. 34. Production of cement. 35. Reclamation of tailings ponds of toxic waste. 36. The warehouses of toxic chemicals of national importance. 37. Thermal power station and other installation for burring with thermal capacity 300 MW or more and also facilities with nuclear reactors. 39. Pharmaceutical factories (with the exception of enterprises on packaging of finished 40. Chemical complexes and factories. drugs). | LOAN NO. 2629-UZB | FINANCED BY: The Asian Development Bank | NOVEMBER 2013 | UZBEKISTAN Environmental Audit Uzbekistan: Talimarjan Power Plant Extension Project November 2013 Final Version • SUBMITTED BY: • IN ASSOCIATION WITH: DOCUMENT CONTROL AND VERIFICATION SHEET Job Title: Expansion of Talimarjan Power Plant with the construction of two combined-cycle plants with a capacity of 450 MW" Project Contract No: ADB LOAN NO. 2629-UZB Document Name: Environmental Audit – November 2013 Document History: Version Date Prepared Checked 1.0 30 November 2013 Natasha Sim Terry Foote 1.1 1.2 Approved ABBREVIATIONS ADB Asian Development Bank CS-MM Corporate Solutions and Mott MacDonald Team CCGT Combined Cycle Gas Turbine DMF Design and Monitoring Framework EA Executing Agency EPC Engineering Procurement Construction GoU Government of Uzbekistan HDEC Consortium of Hyundai and Daewoo H&S Health & Safety HSE Health, Safety, and Environment IA Implementing Agency IC Implementation Consultant IAS International Accounting Standards IFI International Financial Institution JICA Japan International Cooperation Agency PAM Project Administration Manual PFS Project Financial Statements PMU Project Implementation Unit TPP Talimarjan Power Project UFRD Fund for Reconstruction and Development of the Republic of Uzbekistan UZS Uzbekistan Som (currency unit) VAT Value Added Tax WA Withdrawal Application CONTENTS 1. INTRODUCTION ...................................................................................................................... 5 1.1. OVERVIEW ........................................................................................................................... 5 2. RESULTS ................................................................................................................................. 8 3. CONCLUSIONS AND FUTURE AUDITS .............................................................................. 31 FIGURES AND TABLES Table 1: People on Site at the time of the Report ........................................................................... 7 Table 2: People Interviewed During the Audit ................................................................................. 7 Table 3: Overall Questions .............................................................................................................. 8 Table 4: Environmental Checklist .................................................................................................. 10 Table 5: Supervisor Interview Questions ....................................................................................... 31 Table 6: Worker Interview Questions ............................................................................................ 32 Table 7: Summary of Hazard Control ............................................................................................ 33 Table 8: Environmental Induction Checklist .................................................................................. 34 1. INTRODUCTION During November 2013, the Consultant performed the first Environmental Audit on the Talimarjan Power Expansion Project construction site to use as a baseline. CS-MM plans to perform environmental audit reports bi-annually and inspections monthly. GENERAL Audit Number: 1 Weather Audit date: November 2013 General: Sunny with small winds Site visit dates: 6-7 November 2013 Temperature Date of next Audit: May 2014 1.1. OVERVIEW Max 20 Min 15 Method of Audit Location of Audit: Power block construction site Cooling tower construction site Administration building Temporary workers camp Visual inspections Interviews with HDEC and subcontractor (PGU Tupalang) in English and Russian Progress Details: Documents reviewed: HSE Plan, HDEC, September 2013 Draft EMP, HEDC, November 2013 Levelling of ground near the cooling tower Construction of welding workshops Construction of toilets in the power block area Removing of foundations in the power block area Repairs in the administration building Repairs in cafeteria building Temporary workers camp is in operation. Date Signed – Environmental and Social Expert CS-MM Natasha Sim In December 2009, an Environmental Impact Assessment (EIA) and an Environmental Management Plan (EMP) were created for the project by Uzbekenergo and agreed with the ADB. It is a condition of the Loan Agreement between the Republic of Uzbekistan and the Asian Development Bank (ADB) that these plans to be adhered to. In September 2013, HDEC provided an HSE Plan that included a Site Based Management Plan (SBMP) and environmental management plan. It was not apparent that the measures, proposed in the EIA and EMP (2009), were taken into account. Based on the recommendations from the Consultant and the PMU it was decided that HDEC would create a new EMP based on the EIA (2009), EMP (2009), and best practice and agree this plan with the Client. The new plan will then be adhered to by the Contractor and monitored by Uzbekenergo and the Consultant. In November 2013 HDEC produced a draft version of an EMP, which is currently being finalized and translated. Once the official version has been relayed to the PMU, the Consultant will provide comments to ensure the plan is suitable for the Client and ensures minimal negative environmental impacts. For the Environmental Audit presented in this report the Consultant prepared a checklist for evaluation. It is expected that most measures suggested in this checklist will be included in the agreed EMP. All applicable actions for this stage in construction have been evaluated and where non-compliance is observed comments and recommendations have been made. In the future the agreed EMP will be used for monitoring purposes. At the time of the Audit HDEC, one sub-contractor, PGU Tupalang, and CS-MM were on site. Table 1 describes the breakdown of staff on site at the time of the site visit and Table 2 gives the details of those interviewed during the Audit. Table 1: People on Site at the time of the Report Company Position Staff on Site HDEC EPC Contractor 13 CS-MM Consultant 3 PGU Tupalang Sub-Contractor 169 Table 2: People Interviewed During the Audit Name Company Position Contact (email and/or tel.) Jeong-Hyeon Kim Hyundai HSE Engineer Jeonghyean.kim@hdec.co.kr +99 890 444 1239 Husan Khidirov Hyundai HSE Engineer husankhidirov@gmail.com Irina Mametkulova Abdullaevnas PGU Tupalang HR Manager 91 462 79 57 Bazzarov Irkin Nazomutdiyouvich PGU Tupalang H&S Engineer 91 218 65 33 2. RESULTS Both overall questions (Table 3) and specific environmental measures (Table 4) were reviewed and commented on. Table 3: Overall Questions Question 1 Was it possible for the Auditor to review a HSE Plan before? Answer and/or Comments Done Yes. The CS-MM Team Leader, Terry Foote, and the Environmental expert, Natasha Sim, reviewed the HSE Plan and provided comments to the PMU. It is not apparent that the HSE Plan takes into account all of the Environmental Impact Assessment (EIA) or the Environmental Management Plan (EMP) measures. Observe prominent locations to see if HSE policy has been posted (including offices, reception, meeting rooms, changing rooms, etc.) Offices are not yet established on site. However the Policy could be displayed at the temporary workers camp on the display board. 3 Meeting the HSE officer on site Yes, meeting was held with Mr. Kim and Mr. Husan from HDEC. As well as the sub-contractor H&S Officer. 4 Site maps and layout At the moment site maps and layouts related to the environment are not available. We have recommended that these be created (i.e. maps showing location of waste disposal, storage of hazardous material, sampling points, etc.) 2 5 Attend an environmental induction session HDEC The first HSE induction session focused only on H&S and was held on the 31 October 2013. By the end of November approximately 200 inductions have taken place. Currently no environmental induction sessions are taking place however this is necessary. Once environmental induction and training sessions start to take place the Consultant will review them. 6 Attend a site tour We visited the power block area, cooling tower area, and Site Garage/batching plant area 7 Review of the HSE Policy The HSE Policy is displayed in the HSE Plan and the EMP document. It is signed and dated by management and reviewed annually (the next review will be January 2014). The policy is not made readily available to employees and should be included in the environmental induction sessions. Signed and dated by management Commitment to HSE Reviewed annually Made available to employees 8 Are workers made aware and trained on Action to be taken During the safety induction sessions the PPE requirements are explained. The HDEC HSE Engineer monitors this Action to be taken HDEC Action to be taken CS-MM Action to be taken CS-MM Question 9 Answer and/or Comments PPE? through daily site checks. Is correct PPE being used? For the most part. However certain instances were observed where workers were wearing inadequate PPE (gloves with holes in them, no proper safety boots, etc.) Done Action to be taken HDEC 10 Identify key hazard areas and ensure measure have been put in place to control the hazards HDEC HSE Engineer does daily site walks to ensure that all key hazard areas have been addressed appropriately. 11 Observe key working areas - are environmentally safe working practices being implemented? For the most part environmentally safe working practices are being implemented. However employees need to made aware of the environmental practices that need to be improved (based on the comments in Table 5). 12 Observe key working areas – are the safe work practices guidelines available? The guidelines are not readily available on working sites, however given the nature of current construction work this is adequate. Tool Box talks are being held. 13 Ensure alcohol, smoking and drug policy is clear and posted where necessary The alcohol, smoking and drug policy is described in the H&S induction session. It is not posted around the site and should be made available at the temporary workers camp and around site. Action to be taken HDEC Action to be taken HDEC Table 4: Environmental Checklist Question Applic able Method of Inspection Area of Inspection Response 1.0 Air Pollution Control 1.1 Vehicles and equipment should be regularly serviced and in good condition Discussion with HDEC n/a The sub-contractors hire all the equipment themselves but HDEC checks and controls vehicle maintenance programs. 1.2 Dust suppression, particularly on windy days, managed by daily use of water trucks spraying hauling roads Visual Roads within site boundaries Watering trucks are being used to water down the dirt roads on site. 1.3 Excavated or stockpiled soil and sand shall be watered before loading, if there is a risk of dust generation, e.g. if it is fine material or under windy conditions Visual Excavation area in power block The material is not being damped before transportation however damping is not necessary at this stage due to the ambient conditions on site presently. 1.4 Demolition areas should be watered 1.5 Minimize size and duration of materials Ok Not ok Required Action/Additional Comments Overall comments: For the most part air pollution control measures are being implemented adequately, however there are some areas that need to be improved. For example all vehicles transporting the excavated material must be covered. Not applicable at this stage of construction. Visual All areas within site boundaries Presently the size and height of the stockpiles is adequate for the working areas. It should be noted that the EPC Contract section 16.6.3 states that stockpiles will be Question Applic able Method of Inspection Area of Inspection Response stockpiles Not ok Required Action/Additional Comments formed into low mounds, no greater than two meters in height. 1.6 Minimize drop heights for material transfer activities Not applicable at this stage of construction. 1.7 Enforce speed limits and restrict operating hours through roadside villages and settlements (7:00 – 19:00) No equipment being transported through villages and settlements at this stage of construction. Speed limits to be included in the EMP Currently speed limits and working hours on roads though villages is not specified in the EMP. 1.8 Speeds of such vehicles shall be limited, particularly on unpaved areas Visual Roads within site boundaries Some vehicles were seen exceeding the speed limits, however the HDEC HSE Engineer corrected these measures immediately. Speed limit signs are seen on site. 1.9 Soil, sand, and other construction materials on transport vehicles shall be covered Visual Vehicles carrying material within site boundary Comment here Smoke emitting vehicles and equipment shall not be allowed on site Visual Vehicles carrying material within site boundary Tractor was observed to be releasing black smoke (6 November 2013) at the land preparation area for the workers camps. 1.10 Ok Currently soil transported from excavation area is not being covered. HDEC must instruct subcontractors to cover soil, sand, and other construction materials that are being transported on and off site. HDEC must prohibit subcontractors from using smoke emitting vehicles. Method of Inspection Area of Inspection Keep hauling roads in good condition to prevent excessive dust development Visual Hauling roads within site boundaries Not included in the EMP presently, Forbid the burning of coal, waste, or wood on site Visual Within site boundaries No coal, waste, or wood was observed being burnt on site apart from in cooking areas (where wood is used). This is acceptable. 1.13 Reduction of running vehicle engines when parked. Visual Vehicles within site boundary Vehicles were observed to be switched off while being loaded and excessive idling was not observed. 1.14 Only trained personnel will operate machinery Discussion s with subcontractor n/a 1.15 Develop a fire prevention plan Discussion s with HDEC n/a 1.16 Refuelling of vehicles will be carried out at a designed location. Visual and discussion s with HDEC 1.17 Cement debagging should Visual and discussion Question 1.11 1.12 Applic able Response Hauling roads are currently in good condition. Ok Not ok Required Action/Additional Comments Road conditions to be monitored and repaired where necessary. Open fires are to be controlled. HDEC HDEC Section 7.10 of the HSE Plan by HDEC provides a fire prevention plan for the construction site. It is an appropriate plan and is included in the site induction. HDEC Within site boundaries The refuelling station / site garage is currently under construction. At the moment vehicles are being fuelled off site. HDEC Within site boundaries Cement debagging is taking place in sheltered areas. HDEC Question take place in a sheltered area 2.0 Water Control Measures 2.1 Undertake settling and neutralization of alkaline washing water containing excessive cement prior to discharge 2.2 Store all liquid/solid waste properly above ground to avoid spills/leaks 2.3 Store Haz-Mat, e.g. fuels, chemicals, and hazardous waste, in bounded areas to avoid leaks escaping to the ground waters 2.4 Have sewage treatment or appropriate toilets on site. Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments s with HDEC Overall comments: Water control measures need to be improved in the areas of monitoring and sampling and washing facilities for vehicles. Not applicable at this stage in construction. Visual and discussion s with HDEC All areas within site boundaries Prepare action plan. HDEC Waste is stored above ground, however not on impermeable surfaces. It is unclear at this stage what happens with liquid waste. The waste management system must be improved. Refer to section 6.0 of this plan. HDEC Not present (very minimal) on site currently. Prepare action plan. HDEC Chemicals are not currently being stored on site. They are at a warehouse. Visual and discussion s with HDEC All areas within site boundaries The administration buildings are attached to the sewerage system. The working areas are equipped with Toilets. It should be noted for the future that the EPC Contract section 14.4 states that the plant sanitary sewer shall connect the plumbing wastes from buildings, toilets, washrooms, and household and shall be drained by free- Question Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments flowing intra-site networks. All pipes should be laid underground. 2.5 2.6 Washing of equipment and vehicles in designated area Visual and discussion s with HDEC Within site boundaries Washing areas must have an impermeable ground and oil trap Visual and discussion s with HDEC Within site boundaries At this stage of construction it is acceptable, but needs to be built and planned for. There are no washing facilities presently on site. Washing facilities need to be designed and indicated on a site map. HDEC The washing facilities must be built on impermeable ground and include oil traps. HDEC 2.7 Impermeable bases should be in operational areas 2.8 Natural run-off should be diverted from camps and to a neutralization area Visual and discussion s with HDEC Temporary workers camp 2.9 Chemicals and fuels on site should be kept to a minimum Discussion with HDEC n/a Monitoring of underground water through Discussion with HDEC 2.10 There are no washing facilities presently on site. There are presently no operational areas fully constructed. There is currently adequate drainage at the temporary workers camp. Proper drainage with neutralization needs to be planned for the permanent workers camps. Adequate. At the moment there are not many chemicals/fuel on site. Action plan required. HDEC Chemicals are not currently being stored on site. n/a Not currently taking place and points have not yet been HDEC should choose sampling sites and have a Question Applic able Method of Inspection Area of Inspection sampling 2.11 Discharge water from site should be monitored 3.0 Soil Control Measures 3.1 Covering stockpiles should take place during heavy rain (greater than 20 mm) Discussion with HDEC n/a Response Ok Not ok Required Action/Additional Comments chosen. monitoring plan. Not currently happening. HDEC should choose sampling sites and have a monitoring plan (with random sampling). Overall comments: Soil control measures are being implemented adequately, however some improvements can be made in the area of waste management (see section 6.0) and topsoil management. No heavy rain since construction started. Monitor weather forcasts. HDEC However there is a plan to cover stockpiles in the event of heavy rains. 3.2 Stockpiles should be located on flat and sealed areas Visual Within site boundaries All stockpiles are located on flat areas. 3.3 All drainage facilities, erosion and sediment control structures shall be regularly inspected and maintained Visual and discussion s with HDEC Within site boundaries At this stage of construction drainage facilities, erosion, and sediment control structures are adequate, however they will need to be increased in the future. It should be noted for future planning that the EPC Contract section 16.6.1 states that during construction soil erosion and sediment shall be controlled in accordance with requirements contained in the environmental impact assessment. Temporary sedimentation ponds, shall be constructed on site for use during the construction period. 3.4 Topsoil striped and safely stockpiled where it Visual Within site boundaries Excavated soil is being transported 5km from site and recycled for building residential Topsoil should be heaped somewhere and damped, Question Applic able Method of Inspection Area of Inspection Response is available for reuse houses. 3.5 Re-spread saved topsoil Not applicable at this stage of construction 3.6 Ensure good landscaping and erosion control Not applicable at this stage in construction 3.7 Provide wheel washing sites at exit Visual and Discussion s with HDEC 3.8 Only people with adequate training and knowledge should handle fuel and chemicals to avoid spills Visual and discussion s with HDEC 3.9 All roads should have proper drainage (culverts, slopes, etc.) to avoid erosion and manage surface runoff Visual Site exit Within site boundaries Ok Not ok Required Action/Additional Comments ready for reuse. No wheel washing facility currently in operation. However at this stage it’s not necessary due to the low amounts of rain. A wheel washing facility at the site gate area should be built. No fuel is being handled on site at present. Vehicles are being refuelled off-site at the moment while the fuelling station is being built. HDEC There are few operational access roads at the time being and there is no visible drainage control. There has not been heavy rain during the construction period. Drainage will need to be improved and taken into consideration for the final site roads. (Refer to final construction drawings) Drainage may have to be improved on the roads. The EPC Contract section 14.4 states that roadways should have an inclination allowing drainage to the relevant system. The site map should show where this would be located. Question Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments 3.10 Disposal of all wastes appropriately (with formal contracts with waste management companies) Visual and discussion s with HDEC Within site boundaries The waste management disposal system needs to be improved. The waste management system must be improved. Refer to section 6.0 of this plan. HDEC 3.11 Develop a Hazardous Materials and Handling Plan and a Hazardous Waste Management Plan Visual and discussion s with HDEC n/a No hazardous waste management plan at present. The waste management system must be improved. Refer to section 6.0 of this plan. HDEC 4.0 Noise Control Measures 4.1 Create a noise control plan Discussion with HDEC n/a Stated in the EMP that this will take place. No deadline has been sent for it. A noise control plan should be created by the end of December 2013. HDEC 4.2 Inspecting noise level using the construction equipment Discussion with HDEC n/a No inspections are currently taking place, A noise-monitoring plan must be created to include measures from the EPC Contract section 16.4. HDEC 4.3 Schedule activities during daylight hours Visual Within project site boundaries All activities are taking place during daylight hours. 4.4 Equipment should be operated within specifications and capacity Visual Within project site boundaries Not many large machines are currently being used but those that are (excavators, trucks, etc.) are being used Overall comments: Currently no noise monitoring is taken place however noise prevention measures are adequately being implemented at this stage of construction. Question Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments appropriately. 4.5 Equipment should be shut off when not in use. Limit idling time Visual Within project site boundaries Not many large machines are currently being used but those that are (excavators, trucks, welding machines, etc.) are shut off when not in use. 4.6 As a rule, the operation of heavy equipment shall be conducted in the span TIME of 7:00 – 19:00 hours unless otherwise agreed with local residents Visual Within project site boundaries All activities are taking place between 7:00 – 19:00 hours. 4.7 Residents should be informed of activities that might generate excessive noise 4.8 Air intakes, vents, and stacks should be fitted with suitable noise attenuating equipment 4.9 Construction equipment, which generates excessive noise, No activities are taking place off site that would affect local residents. No activities are taking place off site that would affect local residents. HDEC should ensure that the designs include proper noise attenuating equipment. Noise attenuating equipment is standard for Air Intakes and Stacks. No compressors, jackhammers, etc. are currently being used at this stage of construction. It is not always practical to enclose all equipment. Method of Inspection Area of Inspection Response Noise maintained at 70 dB(A) at outside of nearest building from power plant Listening from nearest town Nearest town The nearest town is far away and no construction noise could be heard from the town. This will need to be tested in the future when different site activities are taking place. No noise-testing equipment was used. HDEC 4.11 Equipment should be in good working order, replace broken and worn parts immediately Visual Equipment within site boundaries All equipment being used was in good working order Regular checks to be carried out. HDEC 4.12 Appropriate PPE should be distributed to all workers There is no excessively loud equipment currently being used on site and therefore no ear protection is in use by workers. A stock of ear defenders or in ear noise suppressors to kept. There is currently no complaint mechanism on site. A complaint mechanism needs to be put in place by both HDEC and the sub-contractor. Question Applic able Ok Not ok Required Action/Additional Comments such as compressors, jackhammers, shall be enclosed to prevent noise nuisance 4.10 4.13 4.14 Clarify by signboards on construction sites an/or stickers on equipment outlining how affected parties can lodge complaints Visual and discussion s with HDEC and subcontractor n/a Part of the EPC Inspection n/a HDEC (This is not for sign boards TF) The EPC contract does not As the EPC Contract does not Question contract should have noise emission performance specifications for all major equipment and the plant overall 4.15 Applic able Method of Inspection Area of Inspection Response include performance specifications. of the EPC and discussion with HDEC Have strict routing for vehicles 5.0 Leak and Spill Control Measures 5.1 Develop spill response procedures and provide spill response kits at all Haz-Mat storage areas and work sites. Not ok Required Action/Additional Comments state noise emission and performance specifications for all major equipment, these should be agreed on between HDEC and the PMU and shall meet international standards. HDEC should ensure that the designs include proper noise attenuating equipment. Provide for adequate internal ventilation to allow the plant building to be contained, and avoid the need to allow emissions through doors and other openings 4.16 Ok Designs to be checked. No vehicle routing through towns presently. Action plan required. HDEC Overall comments: As the fuelling station is currently under construction and chemicals are not presently stored on site, these measures are not applicable at this stage. However they must be planned for and a spill response plan should be created. Discussion with HDEC n/a There is no spill response plan currently available. There are no spill kits available A spill response plan should be created by the end of December 2013 and all working areas should be equipped with spill response kits. It should at minimum include measures 5.2 – 5.11. Question 5.2 Fuelling to be done on a concrete surface provided with spill catch tank that can be easily cleaned and all spilled fuel recovered/safety deposited 5.3 All repair and maintenance work must be done either on a concrete surface with oil spill catch basins or oil catch pans provided at all service areas 5.4 Training should be provided to all staff handling fuel and chemicals 5.5 Routinely inspect all equipment handling hazardous materials for leaks and spills 5.6 All fuel where spills and leakage area possible, e.g. the generator, Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments Question Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments must have drip basins installed to prevent leakage 5.7 The recovered materials must be recycled 5.8 Fuelling equipment must be fitted with proper fuel nozzles and devices to avoid accidental spills 5.9 All fuel stored on site should be kept in drums or tanks 5.10 Fuel storage area should be located at a designated place away from ignition and drains 5.11 Proper signage should be displayed at the refuelling area 6.0 Solid Waste Management Control Measures Overall comments: Waste management needs to be improved on site. It is crucial to have plans and procedures in place for when the waste quantities increase. Method of Inspection Area of Inspection Response Create a waste control plan that includes inventory of waste fractions to be expected to be generated during construction for approval of disposal routes by Hokimiyat and SES Discussion with HDEC n/a No waste control plan has been created that describes the estimated waste quantities and disposal methods. Develop a Hazardous Materials and Handling Plan and a Hazardous Waste Management Plan. Hazardous waste shall be identified, classified, handled and disposed of safely Visual and discussion s with HDEC n/a Provide reuse collection containers and used oil collection containers at all construction sites and labour camps Visual and discussion s with HDEC Within site boundaries Question 6.1 6.2 6.3 6.4 Dispose of paper, resin, metals, and Applic able Ok Not ok Required Action/Additional Comments A solid waste control plan should be created by the end of December 2013. Expected waste quantities need to be estimated. HDEC No hazardous waste management plan at present. Develop a hazardous waste management plan. HDEC No waste oil collection containers were observed on site. Waste collection containers need to be provided (for a variety of wastes) in all working and administration areas. HDEC Not applicable at this stage but Plans for selling paper, metals, and other recyclables should Question Applic able Method of Inspection Area of Inspection other recyclable waste fractions to other enterprises for recycling 6.5 Dispose of inorganic solid waste (concrete, bricks, etc) properly after approval by Hokimiyat and SES. Formal contracts with waste management companies should be established. 6.6 After completion of civil works, collect all garbage and waste construction materials from site, and dispose in specially designated places agreed by the SES 6.7 Separate waste disposal area shall be designated on the construction site Discussion s with HDEC n/a Response Within site boundaries Not ok Required Action/Additional Comments must be planned for. be established. HDEC There is a waste company removing household waste from site that has approval from the government and PMU. Get the Hokimiyat and SES to approve the disposal routes. Do not have approval of SES or Hokimiyat. Visual and discussion s with HDEC Ok Establish contracts with waste management companies. HDEC Not applicable at this stage of construction. Put a plan in place. HDEC No waste disposal area (transfer area) has been established yet. A waste disposal area must be established and made known to all sub-contractors. The areas should be indicated on a site map. Question Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments 6.8 Separate collection of waste according to type where possible Visual and discussion s with HDEC Within site boundaries No separate waste collection. 6.9 Reuse and recycle construction waste as much as possible Discussion with HDEC n/a Excavated soil is currently being transported 5km away from site and being recycled for a housing development project. Continue to encourage recycling as much as possible for both household and construction waste. 6.10 Log of waste flows should be kept (including volumes and weights of all waste types) Discussion s with HDEC n/a No waste log flows at present. A log of waste flows (both volume and weight) but be kept. 6.11 Store flammable waste separately Visual and discussion s with HDEC Within site boundaries Flammable waste on site consists of waste oil and leaves. In the future flammable waste (in large quantities) needs to be stored separately. 6.12 Have appropriate waste containers on site Visual and discussion s with HDEC Within site boundaries There should be more waste containers at working stations. Small waste piles near working areas can be seen accumulating. Waste collection containers need to be provided (for a variety of wastes) in all working and administration areas. HDEC 7.0 Emergency Situation Control Measures 7.1 Ensure the contractor records complaints and Overall comments: Aspects of the emergency control measures need to be improved. A complaint mechanism needs to be created, spill kits need to be kept in all working areas, and first aid kits need to be more readily available. Discussion s with HDEC and n/a There is currently no complaint mechanism on site. A complaint mechanism needs to be put in place by both HDEC and the sub-contractor. Question Applic able Method of Inspection Area of Inspection Response Ok Not ok Required Action/Additional Comments responses, conducts resolution monitoring, and includes information on complaints in regular progress reports. subcontractor 7.2 Audit complaint files and verify closeout Discussion s with HDEC and subcontractor n/a There is currently no complaint mechanism on site. The complaint mechanism should include auditing complaint files and ensuring all complaints are closed. 7.3 Notify the public about any noisy activities that will take place Discussion s with HDEC and subcontractor n/a There is currently nobody responsible for community awareness. HDEC should appoint a person to be responsible for informing the community of ongoing activities. 7.4 Require contractors to prepare and organize work implementation schedules and tasks for proper registration for the vehicles and heavy equipments, driving licenses, required skills and experience Discussion s with HDEC n/a The Sub-contractor has a person responsible for all equipment. They are responsible for checking licenses and skills of operators. HDEC collects data and does checks when the sub-contractor comes to site. Question Applic able Method of Inspection Area of Inspection Visual and discussion s with HDEC All areas within site boundaries 7.5 Providing PPE 7.6 No transport or operation of heavy equipment at night 7.7 Education and training of workers on regulations on work safety and risk prevention and to obey them. Following existing regulation KMK 3.01.02-00 “Safety engineering during construction” Discussion s with HDEC and subcontractor Implement accident reporting and investigation procedures with reporting of the root case of individual cases, and analysis of weekly and monthly statistics Discussion s with HDEC and subcontractor 7.8 7.9 Storage of flammable and explosives in a Response All workers on site are wearing PPE, however some violations were seen and presently harnesses are not used. Ok Not ok Required Action/Additional Comments A tight control needs to be kept by HDEC to ensure that all sub-contractors are wearing appropriate PPE at all times. Not applicable at this stage of construction. n/a Induction sessions are taking place by HDEC and daily site instructions are issued by the H&S Officer of the subcontractor. Action HDEC At the moment not all workers have had the safety induction, although steps are being taken to ensure that this happens. n/a HDEC has a procedure for accident reporting and monitoring that is in use and adequate. Small modifications need to be included on the accident forms and these have been discussed with HDEC. The sub-contractor uses the standard government form for accident reporting and will also be required to use HDEC reporting forms. Flammable and explosives are currently not present on site. Explosives should not be required on this site but if they are they must be controlled in a lockable building away from Question Applic able Method of Inspection Area of Inspection Response closed warehouse Ok Not ok Required Action/Additional Comments people and property. 7.10 Regular territory cleaning. Site should be kept clean and tidy. Visual All areas within site boundaries The site is organized and clean. 7.11 Fire fighting equipment on site Visual All areas within site boundaries Fire fighting equipment is available on all working sites. The sub-contractors are trained in fire fighting. 7.12 Fire fighting training for all employees Discussion s with HDEC n/a 7.13 Keep rags and dry sand in case of spillage (absorbent materials) Visual All areas within site boundaries 7.14 Transport oils in special transport Visual n/a 7.15 Chemicals and fuel on site will be kept to a minimum Visual All areas within site boundaries Chemicals are not currently being stored on site. They are at a warehouse. 7.16 Ensure all vehicles meeting safety standards (brakes, lights, tyre conditions, Visual and discussion s with HDEC All areas within site boundaries HDEC will be monitoring and checking sub-contractor maintenance programs. Sub-contractor and HDEC employees are trained in fire fighting. Not all sites have spill kits available. Rags and dry sand (spill kits) should be available at all working sites. HDEC Oil delivery trucks are being used for transportation. Method of Inspection Area of Inspection First aid kits should be provided on all working sites Visual All areas within site boundaries First aid kits are not readily available on all areas of site. 7.18 Comply with labour laws and best practices Visual and discussion s with HDEC All areas within site boundaries Labour laws are being complied with. 7.19 All safety equipment should be examined monthly by a competent person Discussion s with HDEC n/a The HDEC HSE Officer is component to examine equipment and provides daily checks. 7.20 Provide health assessments to employees and subcontractors n/a All workers must go through a medical check before starting work (there is a doctor on site, employed by the subcontractor). 7.21 Site security should be provided Question Applic able Response Ok Not ok Required Action/Additional Comments etc.) 7.17 Visual All areas within site boundaries The sub-contractor has a medical point that is full equipped. There is strict site control for the power block (security, ID badges, etc.) but the cooling tower is accessible by anyone. The EPC Contract Section 17.17 states that the contractor is responsible for controlling and monitoring vehicle and personnel. First aid kits should immediately be provided at all working stations. HDEC A Colour code system to be used. HDEC Site security needs to be improved at the cooling tower area. HDEC Question Applic able Method of Inspection Area of Inspection Response Visual All areas within site boundaries All hazardous work is marked off clearly. 7.22 Safety barriers around hazardous work 7.23 Workers should have access to emergency communication devices Visual and discussion s with HDEC n/a At present, communication devices are limited to cell phones. 7.24 Implement a fitness for work programme Discussion s with HDEC n/a HDEC and the sub-contractor is implementing a fitness for work programme. Ok Not ok Required Action/Additional Comments This should be improved as construction progresses. 3. CONCLUSIONS AND FUTURE AUDITS The Consultant’s largest concern is the lack of an agreed EMP at this stage in construction. A plan should have been discussed and approved to before site-work began, and therefore it is crucial that an EMP be settled before the end of the 2013. It is an essential component of the construction process and a requirement of the ADB. Despite the lack of a formalized plan, negative environmental mitigation measures on site are being implemented adequately however improvements can be made. Control plans for waste management, air emissions, noise, and wastewater must be created and implemented as soon as possible. Environmental induction and training sessions need to be planned for as well. The “Recommended Actions” column in Table 4 describes the measures that need to be improved in more detail. Furthermore HDEC must agree a standard monthly reporting format with the PMU. The report should include: EMP implementation (format could be similar to this audit) Results of any environmental tests (water samples, noise tests, etc.) Copies of applicable contracts or agreements (waste management contracts, agreements with SES, etc.) Statistics on number of environmental inductions, number of workers on site, any environmental accidents (spills, leaks, etc.), and H&S data. The next audit will take place in May 2014 and as previously stated the agreed EMP will be used for monitoring. Future environmental audits will also make use of Table 5, Table 6, and Table 7. In addition, once environmental induction and training sessions are created, they will be reviewed and comments on (using Table 8). Table 5: Supervisor Interview Questions Question 1 Can you describe the HSE Policy? In particular can you describe the environmental aspects of the policy? 2 What processes are in place to ensure that hazards are identified on an ongoing basis? 3 What process is used to control the hazards? 4 How do you ensure the controls are being implemented? 5 How are employees reprimanded for not following environmentally safe working practices? Answer and/or Comments Done Question 6 What systems are in place to ensure that employees have access to PPE and wear them? 7 How do you ensure that everyone attends orientation and HSE induction? 8 Have you received inspections? 9 What inspections take place and how often? 10 What is the reporting process after an incident occurs? 11 What training have you received on emergency procedures? 12 What measures are in place to ensure there is no substance abuse? 13 What happens if someone is not in compliance of this? Answer and/or Comments Done Answer and/or Comments Done Table 6: Worker Interview Questions Question 1 Is the HSE Policy made available to you? 2 Can you describe the HSE Policy? In particular can you describe the environmental aspects of the policy? 3 Are you able to attend environmental training as required? 4 How are you re-assessing hazards in your working area? 5 How are you informed of the controls that will be used to minimize these hazards? 6 Do you understand how to perform your job so that it has minimal environmental impact? Question 7 Is adequate PPE made available to you? 8 Are you provided with company rules? 9 Do you understand the rules? 10 Are the rules enforced consistently with all employees? 13 Do you have a process for removing defective equipment? 14 Were you giving an orientation before starting work? 15 Are you able to bring up safety/environmental concerns at HSE meetings 16 How can you report unsafe/unhealthy working conditions? 17 Are you aware of the procedures for incident reporting? 18 When do you need to report incidents? 19 Did you receive training on your responsibilities in an emergency? 20 How are you able to contact emergency personnel? 21 How is the smoking/alcohol/drug policy communicated? 22 Do you understand what would happen if you were in noncompliance with the policy? Answer and/or Comments Done Answer and/or Comments Done Table 7: Summary of Hazard Control Question 1 Have critical tasks been identified? What is the list? 2 Are the hazards controlled? If so, how are they controlled? Question 4 Are the controls are being implemented? 5 Does the employer use a site specific ongoing assessment process? 6 Are controls being implemented in a timely manner? 7 Are employees aware of the hazard identification process control measures? Answer and/or Comments Done Table 8: Environmental Induction Checklist Question 1 Does everyone have to sign an induction book? 2 Is there an HSE Policy? 3 Is there colour coding of signs? 4 Are the key environmental issues discussed? 5 What are the daily environmental hazards on site? 6 Are environmental responsibilities explained? 7 What are the detailed procedures? 8 Is the handling of chemicals and hazardous substances explained? 9 What hazardous material is on site? 10 Where is it stored? 13 Is the waste management program described? 14 Is the general storage of material on site explained? 15 Dust, fume, and noise control? 16 Water and wastewater management? Answer and/or Comments Positive Negative Question 17 Soil measures? 18 Are instructions given on what to do in the event of an environmental accident? 19 What information do they need to provide? 20 Who should incidents be reported to? 21 Where is the location of first aid boxes? 22 Is there an introduction to what causes fires? 23 Where is fire equipment located? 24 Is there a description of the spill and leak plan? 25 How do they identify hazards and to whom do they report? 26 Who provides the PPE? 27 Why is PPE important in relation to the environment? 28 When should you wear it and what should you wear? 29 Smoking/Alcohol/Drug policy? Answer and/or Comments Positive Negative TA-7548 REG: 450 : 6 , , , : 14-7, 100100 www.nbt.uz , 2014 TA-7548 REG: - , 2014 , - - /EIA (Environmental Impact Assessment) - - - - - (IEE) 450 TA-7548 REG: - 1. , 450 ( , 2014 ) (L2629/2630 43151-023) 1. , ( . .1). 5%1. – . 1: « 450 » 2. 2. ( « С ) « », , « . , , ( », ( , .2). Э , , ». ) ё , . ё ( 1 А . ) – 2013 «Corporate Solutions TA-7548 REG: - , , 2014 Consulting Limited and Mott MacDonald». С ( ) , , - , , . 2. 3. Construction anН DaОаoo IntОrnational Consortium» (К , ( , ) , , . 4. « « »- ( ). «HвunНai EnРinООrinР anН ). : », « . , »- 3. 5, 5. « 1 2010 » 3 , «... – , ( ) TA-7548 REG: - , 2014 , , ё ( , ( )…». « , , ) » , , , , «.. . , , , , , , , , ; (ii) , ( . 19.4. , 9. , . , . 19. ( . , (Site Based Management Plan , SBMP , ё ; (iii) ; . 16.3-16.5 . , 8. , , . 16.1 : (i) ». 6.2 « 2 SBMP) ё ё «.. …». 16. 16.1-16.6. , ё 7. )», , ..» 6. ё ё , , ; (ii) - «.. (i) , ), , , 3 . К 10. 6 – , 4 , , «.. , 11. 07.03.2013 ., 2 ( 3 ), 400-450 2010. , ». 7 ( ), 2 2 – . , 2/3 – 6.2. NШ. SJSC/UгЛОФEЧОЫРШ/ICB-2010-001 25, 27, 39, 3. ) , , SJSC/Uzbekenergo/ICB-2010-001) « EЧРТЧООЫТЧР КЧН CШЧЬЭЫuМЭТШЧ КЧН DКОаШШ IЧЭОЫЧКЭТШЧКХ, 7 . . 6.2 , 4 2013 » ( . 12.11.2010 . « » ( No. Hyundai TA-7548 REG: - , 2014 , (SBMP), . 22.7 - 12. , 7 . 13. 8 – , (b) ( 9 – , ( ), ы чё ы 1 – ё 14. «( ) , , ) ё ы 1, ». , . 2009 (EIA), , . ё , , : , , . 15. . , 2013 ё . - , . 1 30 ( 4.6. 6.5. , , »5 ). ё . . 450 ё « , 2- , - . 16. , , , . ё , , , , , , 6 . 17. , NO, NO2, CO « SO2 . » , , . , . , ( .3-4). . . 5 6 2 ё 2013 TA-7548 REG: - , 2014 , , 3: 4: 18. 2012 2009 - , , . , , ( , . 2013 , ( , . 2013 .) ) . ё , 2013 .7 « » 2013 , - ё ё , . ё » . . - « , , , . 19. . 8 2013 , . , (2009), . 20. « » ( ) «Hyundai Engineering and Construction and Daewoo International Consortium» ( ( ). ( У ССУ)9 , . . 7 ё - 2013 ., 4.2. ё 8 9 , ) HSE Plan ( ё , , , 2013 . 3.1.3- ) TA-7548 REG: - , 2014 , . - 8.11.2013 . , , , , 2013 21. . - . ё ( ) . . , , . , , , . 4. , 22. ё , (. ё . 23. ( 2013 24. , ( . 7), . 9). ( 25. 300 26. . . , . ( . 11). ( . 14). . 10). ё , ( 27. , 8), ( ё , ( ( , . - 1 . 5). , . 2 . ) . 13). , . 12). , ( , , , ). TA-7548 REG: - 5: , , 6: , , 7: 9: 8: 10: , 2014 TA-7548 REG: - , 2014 , 11: 12: 13: 14: 28. , 29. . - , , . , , . . 5. : 30. , . , . 5, .3 31. ..». , , ё , , «.. , , ( . . 35 ё , ). TA-7548 REG: - 32. . . 2013 , 33. , . 35. . – ё 36. ё ё , . , 2009 . 37. , , - ё , , . 34. 38. , 2014 , . , . , . . 1. , 1: # / , 1 ё - 2 – ё – - 3 – - – – 4 / 5 2013 - , – – 6 - – TA-7548 REG: - , 2014 , 1. : : : 450 (%): 5 A B C X X++ – A. – / No. 5 3 B. ы ) К «УЗ КЭ , » ч х ых ч ых У B. ( / ( / ) ( / ) ( ) С , С. , . ( ) . , , . ё 1 TA-7548 REG: - , 2014 , 30 2013 ( . 4.6. ё , 6.5. ). ё . . « 2, , . » -450 , (EIA), , 2009 : . , « » ( , , . ) . NШ. ( ) SJSC/UzbekEnergo/ICB-2010-001 07.03.2013 ., 7 ( ), 27, 39, 25, (SBMP) « ( 16. 16.1-16.6. : ё ; ; . 16.1 6.2 )», , (SТЭО BКЬОН MКЧКРОЦОЧЭ , , SBMP Plan - SBMP) . ё , . (Т) ; (ТТ) , (ТТТ) . 16.3-16.5 TA-7548 REG: - , 2014 , , . . « » (SEMP) ( , ) . . . 8.11.2013 , , . , - . ( 2013 C. ( ) . ) / ( / ) .2 ( / ) , ; ё . , EMP . . ( 2013 ( ) ё . , , ё TA-7548 REG: - , 2014 , / ( / ) ( / ) ) , , , - . . , , « . » - / ( ) . , - 10 EMP/SEMP ( , . , SEMP, 8.11.2013 . - ) , , , . - ( . 2013 - 11 10 11 EMP, ё , , ё . , 2013 ) 2009 2012 . 2013 . , - , TA-7548 REG: - , , 2014 / ( / ) ( / ) . ё Monthly Pro gress Reporrt (Dec. 2013 3) 6. HS SE Mana agement 6.1 Sa afety Man-hours T This Month Cumulative e Descriptio on Man Hours Wo orked Co ontractor Subcontractor Total Contractor Subcontracto or Total 2,610 47,430 50,040 17,090 179,590 0 196,680 0 ealth, Safe ety & Envirronment T Training Status 6.2 He T This Month Cumulative e Descriptio on Co ontractor Subcontractor Total Contractor Subcontracto or Total Number of Tra aining 2 9 11 9 29 38 Training Man Hours H 32 120 152 140 886 1,026 Tool Box Ta alks 26 26 52 87 90 177 afety Inspe ection & Results R 6.3 Sa 6.3.1 1 Daily Work W Site Inspection I n ▶ Checck list (a) PPE : Subco ontractor pre epared all permanent p PPE P withoutt uniform. (b) Liifting Opera ation : Contrractor reque ested them change oldd crane to new one. Talimarja an Thermal Po ower Plant Exp pansion Projec ect 36 Monthly Progress Report (Dec. 2013) (c) Work at Height : subcontractor used harness one lanyard type, but HSE team agreed 2 lanyard types only. So they must change all of the safety harness (d) Excavation : Subcontractor excavated project work area before set up the safety lines and work sign board (e) Scaffolding : Over the 1.2m using scaffold to work if there were no lifelines or lanyard lanyard check point. (f) Welding Operation : Welder must weared specific PPE for a work. (Welding cloth, welding mask welding gloves and so on. (g) Driving Operation : Under the 20km/h drive in the Project area Talimarjan Thermal Power Plant Expansion Project 37 Monthly Progress Report (Dec. 2013) (h) Housekeeping : Before Start and finished work check around the work area to protect accidents. (i) Demolition process : With Civil teams and HSE Teams check the demolition work (noise, work condition, working of equipment and so on.) (j) Noise limit during demolition work at site, power block gate and main office (k) Living condition of employees : In the camp, HSE team allowed each 8 persons can live inside Talimarjan Thermal Power Plant Expansion Project 38 Monthly Progress Report (Dec. 2013) 6.3.2 Weekly Safety Walkthrough ▶ Schedule: Every Monday 10:00 AM ▶ Area: Power Block, Cooling Tower, Batch Plant ▶ Attendant: HDEC HSE Engineer, To’palang HSE Officer, To’palang Site Manager 6.3.3 Training ▶ Work Permit Forms Trainings Talimarjan Thermal Power Plant Expansion Project 39 Monthly Progress Report (Dec. 2013) 6.3.4 Site Inspection ▶ Heavy Equipment Inspection ▶ Equipment Inspection Machine & Tools ▶ Noise level Inspection ▶ Demolition work process inspection ▶ Inspection of living quarters 6.4 Health, Safety & Environment Improvement Plan ▶ Review and revise Environmental Management Plan ▶ 50 Days No accident campaign : Successfully finished campaign without accident and harzardous Talimarjan Thermal Power Plant Expansion Project 40 Monthly Progress Report (Dec. 2013) 7. Photographs Overview of Power Block Area Power Block Area - 2nd Stage Demolition Work Talimarjan Thermal Power Plant Expansion Project 41 Monthly Progress Report (Dec. 2013) Power Block Area - Temporary Toilet Preparation Work Batching Plant Facilities Preparation Talimarjan Thermal Power Plant Expansion Project 42 Monthly Progress Report (Dec. 2013) Batching Plant Facilities Preparation Overview of Cooling Tower Area Talimarjan Thermal Power Plant Expansion Project 43 Monthly Progress Report (Dec. 2013) Cooling Tower Area - Rebar Shop Preparation Work Contractor(HDEC) Camp Temporary Facilities Talimarjan Thermal Power Plant Expansion Project 44 Monthly Progress Report (Dec. 2013) Subcontractor Mobilization Temporary Facilities Truck Maintenance Workshop Preparation Work Talimarjan Thermal Power Plant Expansion Project 45 Monthly Progress Report (Dec. 2013) Customs Warehouse Preparation for Remodeling Works Talimarjan Thermal Power Plant Expansion Project 46 FOR APPROVAL C B Issue for Approval / Issue for Approval / Issue for Approval / DESCRIPTION 25.Jan.2014 07.Jan.2014 07.Nov.2013 REV. . DATE : EMPLOYER/ J.H.KIM Y.H.Jeong T.H.Jung J.H.KIM Y.H.Jeong T.H.Jung J.H.KIM Y.H.Jeong T.H.Jung DSGN CHKD APPD TALIMARJAN TPP UNITARY ENTERPRIZE of SJSC UZBEKENERGO Я « Я Э » « Э » CONSULTANT : CONTRACTOR/ PROJECT/ : : TALIMARJAN THERMAL POWER PLANT EXPANSION PROJECT TITLE/ : ENVIRONMENTAL MANAGEMENT PLAN SCALE NONE / DOCUMENT NUMBER Rev. . B-000-W-64-001 C Environmental Management Plan Rev. C TABLE OF CONTENTS 1. INTRODUCTION / ................................................................................................................ 4 1.1 PURPOSE / 1.2 SCOPE / 1.3 PROJECT SITE MAP ................................................................................................................... 5 2. DEFINITIONS / 3. RESPONSIBILITIES / ................................................................................................................ 4 ................................................................................... 4 ............................................................................................................ 6 ......................................................................................... 8 3.1 PROJECT MANAGER (PM) / ( 3.2 HSE MANAGER / 3.3 ENVIRONMENTAL OFFICER (EO) / ) ............................................. 8 HSE................................................................................ 8 (EO) 9 3.4 4. 5. SECTION MANAGERS (SM) / ( ) ............................... 10 ENVIRONMENTAL MANAGEMENT / ....................................................................................................... 12 4.1 OVERVIEW / 4.2 ENVIRONMENTAL POLICY 4.3 PROJECT ENVIRONMENTAL MANAGEMENT SYSTEM (PEMS) 4.4 ENVIRONMENTAL ORGANIZATION 4.5 COMPLIANCE WITH LEGAL REQUIREMENTS 4.6 ENVIRONMENTAL ASPECTS IDENTIFICATION 4.7 EVALUATION, SELECTION 4.8 ENVIRONMENTAL MEETING / .................................................................................................... 16 4.9 ENVIRONMENTAL TRAINING / ...................................... 17 4.10 EMERGENCY PREPAREDNESS / ............................................................................................... 19 4.11 ENVIRONMENTAL INCIDENT INVESTIGATION, ANALYSIS 4.12 ENVIRONMENTAL INSPECTION 4.13 ENVIRONMENTAL AUDIT 4.14 ENVIRONMENTAL IMPROVEMENT PLAN 4.15 ENVIRONMENTAL ................................................................................... 12 & OBJECTIVES/ ............................................................................... 12 / .................................................. 12 / .......................................................................................... 13 / ........................................................................... 14 & ASSESSMENT / ................................................ 14 & CONTROL OF SUB-CONTRACTORS / .......................................... 15 / & REPORTING / .................................. 19 ......................................... 20 / ............................................................. 22 / .................................................................................. 23 REPORTING .................................................................................................. 23 ENVIRONMENTAL CONTROL AND MONITORING / ............................................................................ 25 5.1 SPECIFIC ENVIRONMENTAL MITIGATION MEASURES /............................................................ 25 5.2 ENVIRONMENTAL PERFORMANCE MONITORING / ................................................................... 27 5.3 AIR EMISSIONS / ................................................................ 30 1 Environmental Management Plan Rev. C 5.4 DUST CONTROL ................................................................... 30 5.4.1 objectives / 5.4.2 dust control plan / 5.4.3 specific control action / 5.5 NOISE CONTROL .............................................................................................. 30 .............................. 30 / objectives / 5.5.2 noise control PROCEDURE / 5.5.3 specific control action / WASTEWATER CONTROL в ....... 34 ......................................................... 36 5.6.2 wastewater control / 5.6.3 specific control action / .............................................................................................. 36 в ........................................ 36 ....................... 38 / .................................................................... 41 5.7.1 objectives / 5.7.2 waste control / 5.7.3 specific control actions / 5.8 .................. 33 / objectives / WASTE CONTROL ........ 31 .............................................................................................. 33 5.6.1 5.7 в .................................................................................... 33 5.5.1 5.6 6. / .............................................................................................. 41 ................................................... 42 POLLUTANTS SPILLAGE CONTROL ..................... 44 / ......................................................................................... 48 5.8.1 objectives / 5.8.2 pollutants spillage control plan / .................................................................... 48 .............................................................................................. 48 REFERENCES / 6.1 ................................................................................... 51 THE HDEC CORPORATE HSE POLICY DOCUMENT / HSE HDEC 51 6.2 THE HDEC CORPORATE HSE MANUAL / HSE 51 6.3 THE HDEC CORPORATE HSE PROCEDURES / HSE 51 6.4 ISO 14001 (ENVIRONMENTAL MANAGEMENT SYSTEM) STANDARDS SPECIFICATIONS / 14001 ( 6.5 HDEC HDEC ) ......................................................................... 51 EHS GUIDELINES FOR THERMAL POWER PLANTS(DEC 19,2008) AND IFC/WB PERFORMANCE STANDARDS ON SOCIAL AND ENVIRONMENTAL SUSTAINABILITY(APRIL 30,2006) / Я HSE (19 Я / 7. (30 2008) 51 6.6 EIA (AGREED WITH ADB, DEC 15,2009) / 2009 ) 51 ANNEXES / 7.1 ., 2008) ( , 15 ., Я .................................................................................................................. 51 CERTIFICATE OF ISO 14001 / 14001 ............................................... 51 2 Environmental Management Plan Rev. C 7.2 CONTRACTOR HSE POLICY STATEMENT / HSE ............... 51 7.3 ENVIRONMENTAL MANAGEMENT PLAN CHART / .......................................................................................................................................... 51 [ANNEX 7.1 CERTIFICATE OF ISO 14001 / 7.1 [ANNEX 7.2 CONTRACTOR HSE POLICY STATEMENT / HSE] 14001]............. 52 7.2 53 [ANNEX 7.3 ENVIRONMENTAL MANAGEMENT PLAN CHART / 7.3 ] ........................................................................................................... 55 3 Environmental Management Plan Rev. C 1. INTRODUCTION / 1.1 PURPOSE / The purpose of this plan is to minimize the adverse impacts on the environment by establishing and maintaining the effective mitigation plans against environmental issues that may arise during the construction, commissioning up to hand over of plant to the EMPLOYER. , , , 1.2 . SCOPE / As per work progress, this plan shall be amended and developed every year if necessary. And this plan will incorporate the conditions and mitigation measures contained in the environmental Impact Assessment (EIA), Environmental Management Plan (EMP) provisions, detailed design and the EMP requirements specified in Chapter VI of the Asian Development Bank (ADB) Environmental Assessment Guidelines, 2003 and ITB requirement. , , . , (EIA), (EMP), EMP, VI ( ), 2003, . The CONTRACTOR shall develop and implement an internationally recognized Environmental Management System (EMS) for all activities related to the Project construction activities in line with the The CONTRACTOR Corporate Environmental Management System and ISO 14001 Standards Requirements (refer to Annex 7.1 Certificate of ISO 14001) (EMS) , , 14001 ( 7.1 . 14001). During the construction period, appropriate measures for environmental conservation and protection shall be continuously taken. All measures shall be in accordance with the contract specification and current applicable local laws and regulations. , . . 4 Environmental Management Plan Rev. C Some important items that shall be considered in order to minimize the environmental impacts are as follows: , , : Air Emission Dust control Noise control Wastewater quality control . Waste management control Pollutants Spillage control, etc. . 1.3 PROJECT SITE MAP / 5 Environmental Management Plan Rev. C 2. DEFINITIONS / Audit / Systematic examination to determine whether activities and related results conform to planned procedures and whether these procedures are implemented effectively and are suitable for achieving carried the required objectives. , , . Continual Improvement / Process of enhancing the environmental management system to achieve improvements in overall environmental performance in line with environmental policy. . Environmental Performances / Measurable results of the Environmental Management System related to the control of environmental aspects, based on Environmental policy and objectives. , , . Environmental Targets / Detailed performance requirement, quantified wherever practicable, applicable to the organization or parts thereof, that arises from the environmental objectives and that needs to be set and met in order to achieve those objectives. , – , , . Environmental (or HSE) Management System / (HSE) Part of the overall management system that facilitates the management of the Health, Safety and Environmental risks associated with the activities of the CONTRACTOR and the Sub-Contractors on site. , , , HDEC, . Environmental (or HSE) Policy / (HSE) Statement by the organization of its intentions and principal in relation to its overall Environmental (or HSE) performance, which provides a framework for action and for the setting of its Environmental (or HSE) Objectives and Targets. (HSE), 6 Environmental Management Plan Rev. C (HSE) . Environment / Surroundings in which the construction activities to be occurred and created an impact an air, water, wastewater, dust, noise, etc to related local society. , , , , , , . 7 Environmental Management Plan Rev. C 3. RESPONSIBILITIES / 3.1 PROJECT MANAGER (PM) / ( ) Environmental responsibilities of PM are given below but not limited to: , : Review and approve strategic Project Environmental (or HSE) Policy and Objectives (HSE). Approve the Project environmental protection plan and other procedures . Define roles, responsibilities and provide resources for ensuring that environmental requirements are implemented and maintained in all concerned areas of Project activities , , . Ensure that Project Environmental Management System is managed in an adequate manner throughout the site organization. , . Ensure appropriate resources are available to support the implementation of the Project Environmental Management System . Review suitability and effectiveness of the Project Environmental Management System, etc. .. 3.2 HSE HSE MANAGER / The HSE Manager shall: HSE : Ensure the development and implementation at site on activities described in this plan and other procedures. , . Assist the Project Manager in all environment related matters , . Manage the HSE organization at site. HSE . Ensure that all activities regarding work are carried out in accordance with the environmental management plan. 8 Environmental Management Plan Rev. C , 3.3 , , . Ensure that the Project complies with the EIA and EMP provisions and applicable local environmental laws and regulations. , EIA EMP . Ensure preparation of a detailed EMP based on the EIA and detailed design complied with the requirements specified in Chapter VI of the Asian Development Bank (ADB) Environmental Assessment Guidelines 2003, covering construction and operation phases. EMP, EIA , , VI ( ), 2003, . ENVIRONMENTAL OFFICER (EO) / (EO) The CONTRACTOR shall appoint an Environmental Officer (EO) who has academic qualifications and having adequate experience in environmental management and monitoring. EO must be aware of the information and knowledge of Environmental Management System (EMS) and Environmental Impact Assessment Report (EIA Report) provided by ADB. ( ), . (EMS) ( EIA), . It is the EO function to advise the Project Manager and HSE Manager on the following main areas: HSE : Proper management and disposal of wastes to the designated area by Uzbekenergo. , . Control of noise and dust pollution Sewage water and drainage control Air and water pollution control General housekeeping Monitoring and report periodically Environmental responsibilities of EO in general are given below, but not limited to: , 9 Environmental Management Plan Rev. C : Ensure preparation of a detailed EMP based on the EIA and detailed design complied with the requirements specified in Chapter VI of the Asian Development Bank (ADB) Environmental Assessment Guidelines 2003, covering construction and operation phases. EMP, EIA , , VI ( ), 2003, . Ensure that the Project complies with the EIA and EMP provisions and applicable local environmental laws and regulations. , EIA EMP . Ensure that the environmental requirements are established, implemented and maintained across the Project site activities, specifically including: , , , : Identification and assessment of environmental aspects. Environmental objectives, targets and environmental management program. , . Monitor adherence to the Project environmental policy & objectives, alerting management of non-compliance, and providing advice on remedial actions, through environmental audits, reviews, inspections etc. , , , . Monitor and verify closeout of actions arising from environmental audits. , . Report periodically to the Project management on the performance of the Project environmental management system. . Prepare and submit environmental monitoring reports to Owner. . 3.4 ( SECTION MANAGERS (SM) / ) Environmental responsibilities of SM are given below, but not limited to: , : Fully aware of Project environmental policy, objective & targets and management programs. 10 Environmental Management Plan Rev. C , , . Understand and apply responsibilities specified in the environmental management system documentation. , . Ensure that the environmental requirements are established, implemented and maintained across the responsible section activities, specifically including: , , , : Identification and assessment of environmental aspects. Environmental objectives, targets and environmental management program. , . Coordinate Project Environmental Control Supervisor. . Support & monitor the implementation, performance and effectiveness of the environmental management system. , . Participate in HSE Committee meetings and take every opportunity to talk to his team about environmental issues. HSE , . Support & ensure that supervisors or foremen are working to focus attention on supervising the most hazardous and significant activities. , . Ensure all corrective actions assigned to his team arising from audits, incidents and environmental reviews are implemented on time. , , , , . 11 Environmental Management Plan Rev. C 4. ENVIRONMENTAL MANAGEMENT / 4.1 OVERVIEW / The management of all environmental aspects of the Project activities shall be developed through a comprehensive Project Environmental Management System (PEMS). (PEMS). The PEMS is controlled by the CONTRACTOR’Ь Corporate HSE Management System providing a required level of environmental standards. PEMS HSE , . The PEMS shall be designed and implemented in accordance with the CONTRACTOR‘Ь Corporate HSE Management System and aligned to ISO 14000 series principles for environmental management system. PEMS HSE 14000 . The PEMS shall address the management actions and commitments associated with environmental matters specific to Project. PEMS , , . 4.2 ENVIRONMENTAL POLICY & OBJECTIVES/ The CONTRACTOR shall establish Project Environmental Policy and Objectives in line with the CONTRACTOR’Ь Corporate HSE policy statement. A copy of the CONTRACTOR‘Ь Corporate HSE Policy Statement is provided in Annex 7.2. HSE HSE . 7.2. 4.3 PROJECT ENVIRONMENTAL MANAGEMENT SYSTEM (PEMS) / (PEMS) The PEMS shall be developed to provide a systematic and structured approach to cover all significant environmental aspects of the Project. It will be based on the CONTRACTOR’Ь Corporate HSE Procedures and cover all local laws and regulations for the protection of the environment. Essentially the PEMS shall provide Project with the structure for: PEMS 12 Environmental Management Plan Rev. C . HSE . , PEMS : Managing the operations in a way that ensures that continual improvement in environmental performance and compliance with local regulation is achieved. , . Establishing and assessing performance against its commitments Setting environmental objectives and targets Developing and effectively implementing appropriate plans and procedures. Primary outcomes of the PEMS are to ensure that all activities associated with the construction of the Project to be complied with regulation or procedure so that adverse effects on the environment could be avoided or kept to acceptable requirements. PEMS , , , , . Obligations to fulfill the responsibilities and accountabilities across all elements of the PEMS involve the participation of both the CONTRACTOR and various Sub-Contractors within the Project. PEMS 4.4 . ENVIRONMENTAL ORGANIZATION / The CONTRACTOR shall establish Project environment organization and appoint Environmental Officer to comply with local laws and legislation and to implement Environmental Management System on site. . The Environmental Management System ensures that the Project Environmental Objectives are met through implementation of technical activities and procedures, a Project HSE Team shall be appointed to perform all the technical activities included in this Environmental Protection Plan and the Corporate HSE Manual. . HSE 13 Environmental Management Plan Rev. C , HSE. TСО CONTRACTOR’Ь HОКН OППТМО SКПОЭв КЧН EЧЯТrШЧЦОЧЭ DОЩКrЭЦОЧЭ ЬuЩЩШrЭЬ ЭСО Project Management Team with specialist advice, consultation, inspection, auditing and directions for the execution of the tasks to comply with relevant laws and legislation and to implement Project Environmental Management System on site. , , , . 4.5 COMPLIANCE WITH LEGAL REQUIREMENTS / The CONTRACTOR shall be responsible for all impacts on the environment which result from Project construction activities. Such impacts may include dust, waste, noise, wastewater, etc affecting those outside the site boundary. , . , , , , . The CONTRACTOR shall comply with all relevant local regulations to the Project. . Newly legislated and revised environmental laws shall be examined in order to determine whether those have an influence over Project activities. Environmental laws and other requirements shall be kept up-to-date. . . The CONTRACTOR shall ensure of the following: : To comply with the EIA and the requirements specified in Chapter VI of the ADB Environmental Assessment Guidelines, 2003. EIA , VI ( ), 2003. 4.6 ENVIRONMENTAL ASPECTS IDENTIFICATION & ASSESSMENT / A wide range of potential environmental impacts is foreseeable from the identification of environmental aspects and assessment of environmental impacts, and many impacts relate directly to construction activities on site. 14 Environmental Management Plan Rev. C , . This plan will incorporate the conditions and mitigation measures contained in the environmental Impact Assessment (EIA) , ( ) The CONRACTOR will clarify the identification and assessment of environmental aspects before construction period: : : A ЬТЦТХКr ЬТЭО’Ь ОЧЯТrШЧЦОЧЭКХ КЬЩОМЭЬ ТНОЧЭТПТМКЭТШЧ and assessment report. . Construction methods may arise public complaints or expected to arise during construction. . Construction equipment to be used for construction. , Utilities and facilities related to the construction , Environmental Impact Assessment, if available , Project HSE specification HSE Current applicable laws and regulations, work practice, etc. , The expected adverse (significant) environmental impacts are as follows: ( ) : Dust 4.7 Noise Improper waste disposal Emissions to atmosphere ETC EVALUATION, SELECTION & CONTROL OF SUB-CONTRACTORS / , 15 . Environmental Management Plan Rev. C The CONTRACTOR shall be responsible for ensuring each the Sub-CШЧЭrКМЭШrЬ’ РШШН environmental performance. The CONTRACTOR shall: . : Conduct meetings before bid submission to address specific environmental requirements. . Include Project specific environmental requirements in bid packages. . Request environmental information from each prospective the Sub-Contractor and evaluate it during the selection process. . Stipulate environmental performance in the contractual agreements between the CONTRACTOR and the Sub-Contractors. . Establish specific training requirements for the Sub-Contractors. . 4.8 Conduct pre-job meetings to address environmental expectation. . Require formal the Sub-Contractor environmental induction course for all new employments at the site. . Review the environmental performance of the Sub-Contractors. . ENVIRONMENTAL MEETING / The CONTRACTOR shall conduct regular environmental meetings and committee with internal organization and the Sub-Contractors to ensure that works are carried out on site with minimum adverse impacts to environment / workers and the public. This environmental meeting will be incorporated in the safety & committee meeting where safety, health and environmental matters are to be discussed at the same time. , , . , , . 16 Environmental Management Plan Rev. C The environmental meeting shall be separately held for the purpose to: 4.9 : Review and discuss environmental incidents and non-conformances generated from Project activities within one week. , , . Review and discuss all site environmental matters. . Review environmental performance of environmental protection plan and other control plans . Review training requirement and practice. ENVIRONMENTAL TRAINING / The CONTRACTOR shall establish procedures to ensure that all personnel and in particular new personnel, or personnel transferred to new assignment are given proper environmental training relevant to their duties. , , , , , . Mandatory training shall be provided in appropriate languages to the workforce as follows: , , : On the first day of duty – Induction Refresh training at regular intervals When training needs are identified during risk assessments The CONTRACTOR shall ensure that all personnel are provided with basic training [i.e. Environmental Induction Course (incorporates environment matters), environmental laws and regulations, Project rules on working at site, emergency evacuation procedures]. And the CONTRACTOR shall keep signed records of training attendance. , ( . . ( ), , , ). . The CONTRACTOR shall ensure that all managers, supervisory personnel including those 17 Environmental Management Plan Rev. C of Sub-Contractors are trained in environmental management system. The CONTRACTOR shall be responsible for identifying environmental training which may be required for the performance of the work and ensure that such training is provided for the personnel concerned to mitigate adverse environmental impact. , , , , . , , . Environmental training will include but are not limited to: , Project HSE (Environmental) policy and objectives HSE ( ) Environmental management program , : Significant environmental aspects identified. Emergency preparedness and response plan / drill in environmental incident such as oil, chemical spillage. , Dust control plan Noise control plan Wastewater control plan , . Solid waste management and on how to identify hazardous or potentially hazardous wastes Pollutants spillage control plan Current applicable environmental laws and regulations MSDS contents of hazardous materials, etc for concerned operational peoples. . . All training information, records and certificates shall be properly documented, kept and made available for verification. , , . 18 Environmental Management Plan Rev. C 4.10 EMERGENCY PREPAREDNESS / The CONTRACTOR shall establish an emergency plan to respond effectively to emergency situations on the site to include but not limited to fire, spills, etc. , , , , . The emergency plan shall be: : Establish evacuation procedures. Assign responsibilities to specific individuals. Provide notification to the Authority and outside agencies such as fire station, hospital, etc. , , . Establish means of communications. Assign locations for emergency centers. Provide in-house emergency responses Include site security and controlled access The information developed shall be documented and communicated appropriately within the site to ensure that the site organization can respond to emergency situations. , . The CONTRACTOR shall establish a program of training, drills and exercises to test and evaluate the preparedness for emergency actions. , . The CONTRACTOR shall, once every six months, organize emergency exercises based on likely site scenarios in which the key site personnel work through their emergency response roles. , , . 4.11 ENVIRONMENTAL INCIDENT INVESTIGATION, ANALYSIS & REPORTING / , 19 Environmental Management Plan Rev. C The CONTRACTOR shall establish procedure to identify, record, investigate and analyze any environmental incidents that occur on site. The investigation and analysis shall identify the root cause and contributory causes of the incidents and formulate measures accordingly to prevent future recurrence of similar incident. , , , . . The investigation of the incident or non-conformance shall include: : Identifying and handling any legislative compliance issues associated with the environmental incident or non-conformance. , . Identifying root causes and taking appropriate action to manage the resulting environmental impact occurring from the incident or non-conformance. , - . Initiating any corrective and preventive actions and confirming effectiveness of actions taken. Any actions taken will be appropriate to the magnitude of problems and commensurate with the environmental risk. . . The CONTRACTOR shall establish procedures to ensure that all personnel including the Sub-CШЧЭrКМЭШrЬ’ аШrФОrЬ СКЯО ЭСО ЬФТХХЬ ЭШ rОЩШrЭ ЬКПОЭв ТЧМТНОЧЭЬ. , , , , . The CONTRACTOR shall keep records of all incidents reports, investigation, analysis and counter measures taken and shall submit details of this in Monthly Report, if required. , , , 4.12 . ENVIRONMENTAL INSPECTION / Project key performance indicators shall be developed to monitor environmental performance prior to construction activities. Monitoring environmental incidents and the close-out of audit and incident action items will be included. The key performance indicators will be regularly monitored, recorded, tracked and communicated. 20 Environmental Management Plan Rev. C . . , , . The CONTRACTOR shall establish procedure to carry out internal environmental inspections at least once per shift. In addition, informal spot checks will be carried out more frequently on critical site activities. . , . A written record shall be kept of the daily inspection findings and the results of the inspections should be brought to the attention of the environmental control supervisor and the section managers having responsibility in the area concerned, together with the necessary remedial action and due date for completion. , , , . Any corrective action should be immediately implemented by the section manager, and followed up by the environment staff, with regular monitoring by safety and environment department at site. , , , . The CONTRACTOR shall ensure that inspections are carried out at a specified frequency which will ensure a high level of compliance with the provisions of the EMS. , , EMS. Inspections which are requested by the statutory requirements shall be carried out at a frequency and in accordance with any procedure given in the relevant legislation. , , , . Inspection records and follow up action plan shall be properly documented. In addition, following any regulatory inspection, the CONTRACTOR shall submit a written report to the EMPLOYER which shall provide details of all aspects of the inspection, if required. . , , , , . 21 Environmental Management Plan Rev. C 4.13 ENVIRONMENTAL AUDIT / TСО CONTRACTOR’Ь HОКН OППТМО ЬСКХХ КЩЩШТЧЭ КЧ ТЧНОЩОЧНОЧЭ ТЧЭОrЧКХ ОЧЯТrШЧЦОЧЭКХ audit team to audit the job site an every year. . The following items should be inspected during internal audits: : Current environmental laws & regulations Responsibilities of Project organization Results of environmental aspects identification & assessment Sub-Contractors compliance report Operational control of environmental protection Training and competence Emergency preparedness Incidents and corrective actions Audits and inspections Report of Environmental improvement plan, etc. . The CONTRACTOR shall periodically review and evaluate the efficiency of the Project EMS in place. EMS . The audits and possible corrective actions should be carried out in accordance with the НШМuЦОЧЭОН ЩrШМОНurОЬ ШП ЭСО CONTRACTOR’Ь HОКН OППТМО HSE AuНТЭ PrШМОНurО. All corrective actions for deficiencies identified during audit shall be implemented by the site to verify the satisfaction of the requirement. In addition, the results of audits and corrective actions should be kept and submitted to the EMPLOYER. – HSE . , . , . 22 , Environmental Management Plan Rev. C 4.14 ENVIRONMENTAL IMPROVEMENT PLAN / The CONTRACTOR shall establish environmental objectives and improvement plans based on incident analysis, audit results and results of environmental aspects identification / assessment, in order to raise the Project EMS. , , / EMS . Project environmental improvement plan will cover at least the following: : Achievement of environmental objectives Corrective actions following environmental incidents , Corrective actions regarding non-conformities observed during internal or external audits, self and imposed inspections , , Review of training and emergency drills Environmental aspects identification & assessment and preventive actions Complaints from local inhabitants or local authorities. . The CONTRACTOR shall review Project environmental improvement plan with the CONTRACTOR’Ь HОКН OППТМО ЩОrТШНТМКХХв НurТЧР ЭСО МШЧЬЭruМЭТШЧ ЩОrТШН. . 4.15 ENVIRONMENTAL REPORTING The CONTRACTOR shall establish environmental reporting of the environmental performance to the EMPLOYER alongside the monthly disposal record. . As a minimum, the monthly report shall include: , : Incident statistics Number of Environment audits refer to plan and follow-up and close-out of corrective actions 23 Environmental Management Plan Rev. C Summary of environmental training Principal Environmental activities performed during the period, etc. , 24 . . Environmental Management Plan Rev. C 5. ENVIRONMENTAL CONTROL AND MONITORING / 5.1 SPECIFIC ENVIRONMENTAL MITIGATION MEASURES / The CONTRACTOR shall implement the specific environmental mitigation measures as follows: : Construction Minimize size and duration of exposed areas and materials. . Inform community of duration and schedule of construction activities. . Water exposed areas during windy conditions. Confine construction activities to defined construction worksites. . . Store chemicals in roofed areas with concrete flooring (if required). . Ensure sorbents are available in areas where chemicals are stored , . Cover all trucks carrying materials off site, , . As far as possible, restrict truck movements to day time hours. , . As far as practical, restrict truck movements to major transport routes as far as possible. , , . Maintain on-site construction vehicles and equipment as well as vehicles travelling to and from the site in good condition. , , , , . Program delivery and removal of materials to avoid clashes with peak hours. . Maximize use of large trucks (15~20 tons) to transport construction materials. (15 – 20 25 ) Environmental Management Plan Rev. C , . Use temporary waste storage area for domestic waste with the following characteristics : - : Located away from living and eating areas. - Concrete floors with bund to prevent overflow - Weatherproof roof, Securable bins , - Fencing and signage prohibiting entry to authorized personnel , - Separation of storage of hazardous and non-hazardous waste Ensure all waste is separated into non-hazardous and hazardous/potentially hazardous before reuse, recycling or transport to landfill. / , . Ensure that fire protection equipment is present on site during burning and staffs are trained in its use (if required, but prohibited burning, strictly). , , . Prohibit disposal of waste to KMC (Karshi Main Canal) and other areas of the site. ( ) . Undertake timely repairs of any malfunctioning construction vehicles and equipment. Confine noisy activities to day time. .. . Implement well-organized sanitation using temporary trench latrines. , . Locate latrines away from living and eating areas, away from areas with high ground water table and at least 100m away from KMC. , 100 . Develop dedicated area for storage of recycled material away from active construction works and near site access point. . Admin. / 26 Environmental Management Plan Rev. C Maintain clean and orderly construction camps. Provide a clean water supply at the construction worker camp. Provide adequate rubbish bins and regular dispose of waste. . . . Regularly disinfect toilets Regularly backfill and re-dig toilets. . . Provide rubbish bins in latrine area for collection of solid waste. . Provide Construction workers camps in good condition.(water quality, public health impacts caused by worker sewage) ( , , ) / Batch plant/Workshop / Alkaline wash water containing excessive amounts of cement will be settled and neutralized before discharge. , , . Treat oily wastewater in coalescence separator before discharge. . HSE / HSE Educate workers on the need to maintain hygienic conditions at the worker camp. .. Train construction staff in clean up procedures for spills. . Ensure that truck drivers are educated on road safety requirements. , . Install signage encouraging use of rubbish bins on site and in construction camps. , . Monitoring the level of noise in site boundary Control and operation the storage area for flammable materials and chemical . 5.2 ENVIRONMENTAL PERFORMANCE MONITORING / 27 Environmental Management Plan Rev. C The CONTRACTOR shall conduct self-monitoring of its environmental performance in terms of: : Implementation of mitigation measures. . Monitoring program specified in the table below. . Environmental Performance Monitoring Program / Aspects to be monitored Location Throughout Project site 1. No dumping of waste outside Project site or in canal Throughout Project site 2. General site condition and cleanliness 3. Covering of all trucks moving to and from site , At site exit point Means of monitoring Frequency Observation Daily Observation Weekly Observation Daily 4. Registration papers and compliance certificate of construction vehicles with local Government - 5. Conditions at temporary waste storage areas, including security at areas and separation of hazardous and non-hazardous waste Waste storage areas , 28 Observation Observation Random checks Daily Environmental Management Plan Rev. C . 6. Conditions at construction workforce toilets Project site . 7. Evidence of marking of worksite boundaries Project site 8. Condition and effectiveness of erosion and sediment controls 9. Stabilization, rehabilitation and landscaping of all land surfaces affected by construction activities located outside the site perimeter boundary in accordance with Landscape Rehabilitation and Maintenance Plan requirements , Project site Areas identified in Landscape Rehabilitation and Maintenance Plan , Observation Daily Observation Weekly Observation Observation After heavy rain Biweekly , , 10. Use of non-reflective wall and roof cladding where possible and practical Project site Inspection of construction drawings Before commencement of construction , . Exposed areas throughout Project site 11. Dust generation during windy conditions 12. Number and type of community complaints received Project site 29 Observation Review of Complaints During windy conditions Monthly Environmental Management Plan Rev. C 5.3 AIR EMISSIONS / TСО CONTRACTOR’Ь rОЬЩШЧЬТЛТХТЭТОЬ аТЭС rОРКrН ЭШ КТr ОЦТЬЬТШЧЬ ЬСКХХ ЛО ЭШ: : Minimize emission of dust, exit flue gases into the atmosphere caused by vehicles and equipment for construction by reducing idle time , , . Identify all possible air pollution sources related to construction activities in a method of statement as well as procedure to minimize emission into air. , , . Ensure the CONTRACTOR’Ь ОquТЩЦОЧЭ ТЬ rОРuХКrХв ЬОrЯТМОН КЧН ЦКТЧЭКТЧОН ЭШ ЛО ТЧ good condition. Report any signs of engine not running efficiently like black smoke, poor fuel economy and performance to the appropriate manager. , . , , , , . Ensure hazardous materials are identified during works and notify the EMPLOYER immediately. . 5.4 DUST CONTROL / 5.4.1 OBJECTIVES / To minimize the nuisance impact on surrounding communities of dust generation during construction activities. . 5.4.2 DUST CONTROL PLAN / Dust control plan shall be compiled and implemented for the construction phase and the following key issues included: , : Carry out watering of exposed areas and materials during windy conditions. . Minimize size and duration of exposed areas and materials. . Limiting vehicle-entrained dust from unpaved roads through traffic control measures. E.g. limiting vehicle speeds and restricting traffic volumes. 30 Environmental Management Plan Rev. C , . , . . . Covering trucks during transport of materials and impose speed limits. . 5.4.3 SPECIFIC 5.4.3.1 ACTION / DRILLING & BREAKING / Where breaking of rock/concrete is required, watering shall be implemented to control dust, water sprays shall be used during the handling of excavated material at the site and at active cuts excavation and fill sites where dust is likely to be generated. , / , , , . Where drilling of rock is required, dust controls, including watering prior to drilling to wet down the rock face, shall be implemented to control fugitive dust. , , , , . 5.4.3.2 CONTROL MATERIAL HANDLING / - The heights from which excavated materials are dropped shall be controlled to a minimum practical height to limit the fugitive dust generation from unloading. , , . All stockpiles of aggregate shall be enclosed or covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet. . 5.4.3.3 VEHICLE DUST / As far as possible, restrict truck movements to day time and restrict truck movements to major transport routes. , . 31 Environmental Management Plan Rev. C Maintain vehicles traveling to and from the site in good condition. , , Effective water sprays shall be used on the site to dampen potential dust emission sources such as unpaved areas used by site traffic and active construction area. , , . Vehicles transporting materials that have the potential to generate dust shall have proper fitting side and tail boards. , , , . Materials transported by vehicles shall be covered entirely by clean impervious sheeting, with the cover properly secured and extended over the edges of the side and tail boards to ensure that the materials do not leak from the vehicle. , , , , , . Materials shall also be dampened, if necessary, before transportation. , , . In order to prevent earth movement from the site due to construction activity and run off onto public road, drains, the site shall be inspected regularly. , , . On-site vehicle speeds shall be controlled to reduce dust re-suspension and dispersion by traffic within the sites. . 5.4.3.4 EXCAVATION / The working area of any excavation or earth moving operation shall be sprayed with water before and after the operation so as to maintain the entire surface wet . The amount of soil exposed and the dust generation potential shall be kept as low as possible. This can be accomplished by surface compaction, temporary fabric covers, minimizing the extent of exposed soil and the prompt re-vegetation of completed earthworks. . , , . 32 Environmental Management Plan Rev. C Excavate any ground contaminated by spillage of fuel or leaked oil/hydraulic fluids and arrange for disposal at the waste disposal site approved by the EMPLOYER. , / , , . 5.4.3.5 SITE CLEARANCE / The working area for the removal of boulders, poles, pillars or temporary or permanent structures shall be sprayed with water before and after the operation so as to maintain the entire surface wet. , , , . 5.5 NOISE CONTROL / 5.5.1 OBJECTIVES / 5.5.2 To adhere to the noise regulations as implemented within the noise impacted areas. , . To comply with the occupational noise regulations of Local. To minimize noise impacts on the neighboring residential area (Nuristan town 1km far from project site). . . ( 1 ) NOISE CONTROL PROCEDURE / Noise Control Procedure will be set in accordance with EIA. Noise Control Procedure shall include the following measures for good practice: . : Inform community of duration and schedule of construction activities. . Consider use of temporary acoustic barriers or exhaust mufflers if disturbance to surrounding land use is found to be occurring. , . Equipment shall be operated within specifications and capacity (eg. Don’t overload machines) ( . . ). Equipment shall be operated in as diversified a manner as possible (i.e. if possible, spread operation of equipment throughout working periods rather than operating 33 Environmental Management Plan Rev. C several items simultaneously). ( , , , ). Equipment shall be turned off when not in use. , . As far as possible, restrict truck movements to day time and restrict truck movements to major transport routes. , . Partly finished buildings shall be used to accommodate pumps, generators, compressors and saws. , , . When using pile drivers, jack hammers, and rock drills for blasting activities, select the time when the environment is least sensitive to noise impact preferably during normal working days daytime hours. , , , , . Arrange proper locations of concrete batching plants, electric power stations, etc. as ЬШ ЭШ ЦТЧТЦТгО ЧШТЬО’Ь ТЦЩКМЭЬ ШЧ КММШЦЦШНКЭТШЧ ХТПО ШП ОЦЩХШвООЬ КЬ аОХХ КЬ ШП residents in the Project area. , , . Inspect noise level during the construction of construction equipment as so to determine proper working schedule as so to ensure that noise level is satisfied with the allowable noise level, referred to the EIA in compliance with local regulation. , . 5.5.3 SPECIFIC CONTROL ACTION / Noise emissions from construction sites can be minimized through good site practice, selecting quiet plant and quiet working methods and through the use of temporary barriers. To reduce impact of noise to the residential area from operation of vehicles and equipment for site, the speed of vehicles and other equipment shall be limited and noise from operation of the equipment shall be minimized. , . , 34 Environmental Management Plan Rev. C . 5.5.3.1. NOISE-PRODUCING EQUIPMENT CONTROL / Maintain construction vehicles and equipment in good condition. . Undertake timely repairs of any malfunctioning construction vehicles and equipment. . Confine noisy activities to day time hours. . Mobile plant shall be located as far away from noise sensitive receivers as possible. . Monitor the levels of noise created by the heavy equipment. 5.5.3.2. TEMPORARY NOISE BARRIERS / In general, noise barriers located between noisy construction activities and noise sensitive receivers can provide noise reduction from screening. , , . Movable noise barriers can be located close to noisy plant or between noisy construction activities and noise sensitive receivers in order to achieve a certain level of noise reduction. . Material stockpiles and other structures shall be effectively utilized, where practicable, to screen noise from on-site construction activities. , , . 5.5.3.3. SCHEDULING OF CONSTRUCTION ACTIVITY / Activities may be scheduled to minimize noise generated at certain areas during periods which may be particularly sensitive to noise , , . 35 Environmental Management Plan Rev. C Works using machines or vehicles that generate noise shall be prohibited in the midnight and the dawn. , , . Program delivery and removal of materials to avoid clashes with peak hours. . Inform community of duration and schedule of construction activity. . 5.6 WASTEWATER CONTROL / 5.6.1 OBJECTIVES / To minimize of water being contaminated. To minimize deterioration of ground water and surface water quality . 5.6.2 WASTEWATER CONTROL / The wastewater control procedure will be set in accordance with the EIA. The wastewater control shall include the following details: . : Shall identify sources of wastewater, and state the collection facilities that are to be used to prevent pollution, as well as the method of disposal of the contaminated water. , , . The control plan for wastewater generated from concrete batching plant operation. , . Water from washing large concrete-mixing equipment (mixers and the like) shall not be discharged overland. ( ) . Undertake settling and neutralization of alkaline washing water containing excessive cement prior to discharge. , , . All washing of equipment or machinery shall be undertaken in designated areas (e.g. workshop or maintenance areas), and these areas must be equipped with a suitable impermeable floor and sump/oil trap. The use of detergents for washing shall be restricted to low phosphate and nitrate containing. 36 Environmental Management Plan Rev. C ( , ), / . . Workshops, fuelling depots and washing areas shall be bund. , . Oil collected in grease traps shall be collected by the appointed waste disposal contractor. , , . Any wastewater or spilled fuel collected within bund area around the fuelling area shall be disposed of as hazardous waste. , , . Heavy rain water control plan is to be designed and implemented for the construction phase of the Project. This shall be prepared by the CONTRACTOR prior to commencing construction. The control plan shall include the following details: . . Actions to address the reduction of surface water run-off and resultant erosion. : . Natural run-off shall be diverted away from any camps (i.e. office area used by the CONTRACTOR and Sub-Contractors on site) towards the rain water drains where these are available. ( . . , ) , . Special care must be taken in areas susceptible to erosion, e.g. steep slopes. The CONTRACTOR shall ensure that sand, silt and silt-laden water do not enter the heavy rain water drain system, or KMC. The CONTRACTOR shall appropriate measures to limit erosion and prevent silt and sand entering drainage or KMC due to construction activities. , , , . , , , . . , : Temporary fences shall be erected and maintained to ensure that activities are conducted within the demarcated area, and thus limit impact on the environment. , 37 Environmental Management Plan Rev. C , . All hazardous material storage areas shall be designed to reduce risk of spillages. All materials shall be covered during transport to prevent them from spilling. If there is a risk of contamination of heavy rain water, all stockpiles shall be covered to be kept out of the rain. . . , . Contaminated rainwater and other run-off from construction site shall be contained. Construction of dirt trap, interceptor pond and the attenuation dam (if required) shall be commenced as early as possible in the construction phase. . , ( ) . In the event of a spill which may contaminate rainwater, the spill control procedures shall be implemented immediately. , , . Monitoring the underground water by sampling of underground water at site will be around four (4) points. The location will be qualified and used for periodic sampling. 4 ( ) . . 5.6.3 SPECIFIC CONTROL ACTION / 5.6.3.1 AT THE START OF SITE ESTABLISHMENT / Channels, earth bund walls or sandbag barriers shall be provided on site to direct rain water to silt removal facilities. , . . , . 5.6.3.2 DEBRIS IN KMC / 38 Environmental Management Plan Rev. C Any oil, solid, noxious or floating materials shall not be discharged into canal. And all water discharged shall be reasonably free of impurities. , , . . 5.6.3.3 SOIL EROSION AND SEDIMENTATION CONTROL / Minimize size and duration of exposed areas. Undertake progressive stabilization of exposed areas. . . During construction of fuel oil, minimize the excavation in this area to protect from erosion. , . If excavation of soil cannot be avoided during the rainy season, or at any time of year when rains are likely, exposed slope surface shall be covered. , , . The overall slope of the site shall be kept to a minimum to reduce the erosive potential of surface water flows, and all trafficked areas and access roads protected by coarse stone ballast. , . All drainage facilities, erosion and sediment control structures (if required) shall be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rains. Deposited silt and grit shall be removed regularly and disposed of by spreading evenly over stable. , ( ) , . . Open stockpiles of construction materials (e.g. aggregates sand and fill material) shall be covered during rains. Measures shall be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system. ( , ) . , , . 39 Environmental Management Plan Rev. C All vehicles and plant shall be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and sited wheel washing bay shall be provided at site exits and wash-water shall have sand silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. , , , . , . All road works shall be separated from surface waters with berms or other fencing materials that will contain loose soils. , . All roads shall be properly sloped and have adequate culverts to manage runoff. . Plant site perimeter should occur as much as possible to restore lost natural erosion control. . Earthworks to construct drainage ditches and to lay subsurface drainage conduits (if required) should separate activity areas from surface waters with the placement of berms or other fencing material to contain loose soils during construction. ( ) . 5.6.3.4 FUEL TANKS / All fuel stored on site shall be kept in drums or in bulk tanks which in either case shall be located at a designated place away from any source of ignition or open drain which dШОЬ ЧШЭ ХОКН ЭШ КЧ ТЧЭОrМОЩЭШr, КЧН ЬСКХХ ЛО ЩrШЩОrХв ХКЛОХОН. A “NШ SЦШФТЧР” sign shall be displayed at the storage location and a charged fire extinguisher of the correct type kept on standby. , , , , , . . 40 « » Environmental Management Plan Rev. C Any spillage of fuel shall straight away be absorbed using sand or other absorbent materials, which shall be disposed of as contaminated waste. , . All fuel tanks and storage areas shall be provided with concrete embankments to readily contain spills. . Treat oily wastewater in coalescence separator prior to discharge. . 5.6.3.5 SEWAGE DISPOSAL/HOLDING TANKS / / Sewerage system will be designed and installed to carry all wash and wastewater, sewage, such as arrangement of pits. Where a public sewer system is available, all plumbing fixtures and sewers shall be connected to it in accordance with applicable laws and regulations. , , . , , . Sewage shall be collected prior to disposal. Effluent shall comply with legal guidelines for emissions into the environment, as appropriate. . . Building temporary water treatment works (permeable digestion tank) for construction workers and defining special waste disposal area in order to avoid defecation and throwing domestic waste, leading to environmental pollution. ( ) , , . 5.7 WASTE CONTROL / 5.7.1 OBJECTIVES / To maximize the internal and external recycling of materials. . 41 Environmental Management Plan Rev. C 5.7.2 To minimize the volume of solid waste requiring disposal by landfill. , . WASTE CONTROL / Waste Control Procedure will be set in accordance with EIA. Waste Control shall be implemented for the construction activities. This shall: . . : Incorporate the following waste control hierarchy to mitigate environmental impacts: : Minimize the generation of waste Re-use the waste during construction Re-use or recycle waste streams to other users at other locations Dispose unusable waste streams at permitted waste disposal facilities. . The system for collecting, sorting, disposal and recycling of waste shall be clearly described in the waste control plan. This shall include: , , . : A separate waste disposal area shall be designated on the construction site, which contains clearly demarcated skips and bins to allow different types of waste to be segregated at source: domestic, metal scrap, used oil, paper, hazardous etc , : , , , , . . The CONTRACTOR shall provide sufficient bins with lids to store the solid waste produced on a daily basis. Bins shall not be allowed to become overfull and shall be emptied as a minimum on a weekly basis. , . . Odor, water quality and soil impacts associated with uncontrolled waste disposal , , . Implement adequate numbers of rubbish bins around construction site and in construction camps 42 Environmental Management Plan Rev. C . Install signage encouraging use of rubbish bins on site and in construction camps , . Include information on solid waste management in construction worker training program including information on how to identify hazardous or potentially hazardous waste , , . Develop dedicated area for storage of recycled material away from active construction works and near site access point . Prohibit disposal of waste to KMC and other areas of the site . The waste sorting and temporary storage area shall be permanently controlled by an environmental officer to ensure compliance with the waste sorting and disposal requirement. . The CONTRACTOR shall ensure that the waste control of the Sub-Contractors are suitably qualified and equipped to manage the waste generated during construction. , , . All wastes shall be disposed of off-site at an approved landfill site. (as per type of waste) ( ). The CONTRACTOR and its Sub-Contractors will take all necessary measures to prevent any discharge of any substances, which may result in pollution or be deleterious to life or the surrounding environment. , . Solid waste will be stored in predetermined collection points prior to their removal and disposal by the appointed contractor . Wood and other scrap material with a commercial value shall be separated and stored in segregated areas prior to removal. . 43 Environmental Management Plan Rev. C Oil and other lubricants shall be collected in drums and disposed of in accordance аТЭС ЭСО CONTRACTOR’Ь ТЧЬЭruМЭТШЧЬ. . The dead batteries will be given to specialized organizations for reuse . Sharps containers will be provided for medical facilities (for syringes, suturing kits and needles) and also clearly identified bagging for infectious or contaminated items. ( , ), . Adequate drainage and sewerage facilities (if required) designed and installed in КММШrНКЧМО аТЭС ЭСО CONTRACTOR’Ь ЬЩОМТПТМКЭТШЧЬ. ( ) . Siting and provision of concrete wash areas and disposal area. . Identification of disposal areas for non-contaminated materials such as spoil. , . Appointment of approved contractor for the removal of hazardous and solid waste to existing incineration and landfill areas approved by Hokimiyat and SES. . 5.7.3 SPECIFIC CONTROL ACTIONS / 5.7.3.1 EXCAVATED INERT MATERIALS / Excavated materials are not considered likely to cause adverse impacts, since they may be possible to be used as reclamation fill, which is considered a useful reuse of the material. Any uncontaminated inert material may be delivered to public fill site. , , . . Surplus excavated material, quarry overburden, rock rejected for aggregate, aggregate surplus to the requirements and the like shall not be discarded indiscriminately. , , , , . Different types of surplus excavated materials shall be deposited separately in the spoil dumps designated for the purpose outside the Project site. , . 44 Environmental Management Plan Rev. C 5.7.3.2 CONSTRUCTION & DEMOLITION WASTE / Careful planning and good site management can minimize over ordering and waste of materials such as concrete, mortars and cement groups. If feasible, the noise enclosure shall be designed so that the materials are reusable after it has been dismantled and removed. The design of formwork could maximize the use of standard wooden panels so that high re-use levels can be achieved. Alternatives such as steel formwork or plastic facing could be considered to increase the potential for re-use. , , . , , . , . , , . Disposal of construction waste can either be at a specified landfill, or a public dump. , 5.7.3.3 WASTE FROM VESSEL / Not Applicable. . 5.7.3.4 ( . HAZARDOUS ) (CHEMICAL) WASTE / For the process which generates chemical waste, it may be possible to fine alternatives which generate reduced quantities or even no chemical waste, or less dangerous types of chemical waste. The management of hazardous waste causes number of problems in practice. The wide range of materials and chemicals involved such as oil, lubricants, cutting oils, sludge, paints etc. Hazardous waste shall be identified, classified, handled and disposed of safely. , , , , . . , . , , , , , . Types of hazardous waste: : 45 , Environmental Management Plan Rev. C Fuel, waste oil, paints and contaminated material with oil , , Sludge contaminated with heavy metals , Corrosives, including acids and alkalis , Other hazardous substances Containers used for the storage of chemical wastes shall: , , : Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed , , , , . Store chemical in roofed areas with concrete flooring. . Display a label. Proper labeling is essential. . . The storage area for chemical waste shall; : Be located away from surface water bodies. . Be constructed with a weatherproof cover, concrete floor with bund, and with adequate securable storage bins for waste. , . Have appropriate signage Be clearly labeled and used solely for the storage of chemical waste. . Be enclosed on at least 3 sides. . Have adequate ventilation. . Be arranged such as to separate incompatible materials. , . Disposal of chemical waste shall: : Treated by a licensed waste collector. . Be to a facility licensed to receive chemical waste, such as the chemical waste treatment facility (which offers both a chemical waste collection service and supply the necessary storage containers). , 46 Environmental Management Plan Rev. C , ( , ). Hazardous and toxic waste shall not be disposed of on the water. . Hazardous waste shall be removed from the site property within 60 days. 60 . Hazardous waste shall not be dumped onto the ground, into rain water sewers, or into sanitary sewer system. , . 5.7.3.5 FOOD WASTE / ( ) Catering wastes is divided into food waste and non-food waste. . All organic food waste generated by kitchen facilities to be disposed of at the landfill. , . Food waste shall be daily removed from the kitchen. . Food waste shall always be contained in plastic bags for disposal to prevent pest like flies and rats e.g. from breeding. , , . Non-food waste (beverage cans, packing materials, etc.) shall be collected in separate containers. ( , .) . 5.7.3.6 (CATERING) GENERAL REFUSE / General refuse generated on-site shall be stored in enclosed bins or compaction units separate from construction and chemical waste. A reputable waste hauler shall be employed to remove general refuse from the site, separately from construction and chemical wastes, on a daily or every second day basis to minimize odor, pest and litter impacts. , , . , , . General refuse is generated largely by food service activities on site, so reusable rather than disposable dishware shall be used if feasible. Aluminum cans are often recovered from the waste stream by individual collectors if they are segregated or easily accessible, so separate labeled bins shall be provided if feasible. 47 Environmental Management Plan Rev. C , , , . , , , 5.8 . POLLUTANTS SPILLAGE CONTROL / 5.8.1 OBJECTIVES / To minimize negative environmental impacts through rapid and effective containment and clean-up actions. . 5.8.2 POLLUTANTS SPILLAGE CONTROL PLAN / The CONTRACTOR shall develop and implement a pollutants spillage control plan prior to the start of construction activities. Procedures detailed in the Material Safety Data Sheet (MSDS) for hazardous materials shall be included in this plan and followed in the event of an emergency situation. . , , . The CONTRACTOR shall ensure compliance with the following and where necessary, include details of how this will be achieved in the pollutants spillage plan. , , , , . 5.8.2.1 CONTAMINANTS OF SPILLAGES / The CONTRACTOR shall ensure there is no contamination of the soil as a result of spills from any workshop and other equipment maintenance facilities. , , . Any workshop shall have a smooth impermeable (concrete or thick plastic covered with ground) floor. The floor shall be bund and sloped towards an oil trap or sump to contain any spillages. ( , ). . 48 Environmental Management Plan Rev. C Pumps and other machinery requiring oil, diesel, etc. that is to remain in one position for more than two days shall be placed on drip trays. The drip trays shall be emptied regularly and the contaminated water disposed of off-site at a facility capable of handling such wastewater. Drip trays shall be cleaned before any possible rain events that may result in the drip trays overflowing and before long weekends and holidays. , , , , . , , , . , , . All vehicles and equipment shall be kept in good working condition and serviced regularly. . All equipment that leaks onto the ground shall be repaired immediately or removed. , , . If servicing and fuelling of vehicles and equipment takes place on site, this shall occur at dedicated and properly equipped facilities. All waste generated by these activities shall be managed as per the Waste Control Plan and the Wastewater Control Plan. / , . , . If diesel or oil refueling is to take place on the construction site then the surface under the refueling area shall be protected against pollution to the ground. , . When servicing equipment, drip trays shall be used to collect the waste oil and other lubricants. Drip trays shall also be provided in construction areas for stationary plant (such as compressors) and ПШr “ЩКrФОН” ЩХКЧЭ (ЬuМС КЬ ЬМrКЩОrЬ, МrКЧОЬ, ХШКНОrЬ). , . ( , ) « » ( , , , ). The CONTRACTOR shall not change oil or lubricants anywhere on site except at designated locations, not unless if there is a breakdown or an emergency repair. If emergency repairs are required outside of designated areas, the CONTRACTOR shall take proper control measures prior to commencing such activities and shall ensure that appropriate absorbent materials and/or drip trays are available to collect any oil, fluid, etc. , 49 Environmental Management Plan Rev. C , . , , / , 5.8.2.2 . CLEAN-UP SPILLAGE / Emergency procedures shall be developed and communicated to all personnel such that they are aware of the procedures to be followed for dealing with spills. The procedures shall include identification or responsible personnel and reporting procedures, contact details of emergency services, etc. , , . , . Procedures detailed in the MSDS for hazardous materials shall be followed in the event of an emergency situation. , , . The CONTRACTOR shall ensure that the necessary materials and equipment for dealing with spills is available on site at all times. , . The CONTRACTOR shall ensure that there is always a supply of absorbent materials readily available to absorb / breakdown or where possible, where encapsulate minor chemical / oil spillages. , , / , , / . Any waste water or spilled fuel collected within the bund around the refueling area shall be disposed of as hazardous waste. , , . The CONTRACTOR shall remove all oil, petrol, and diesel-soaked sand immediately and shall dispose of it as hazardous waste. , , , . Excavate any ground contaminated by spillage of fuel or leaked oil/hydraulic fluids and arrange for disposal at the waste disposal site approved by competent Authority. , / , , . If spillages of materials occur during transportation, spillages shall be cleaned-up immediately and transported to the shelter for possible use or disposed of at the appropriate disposal facilities. 50 Environmental Management Plan Rev. C , . Train construction staff in clean-up procedures for spills. . 6. REFERENCES / 6.1 THE HDEC CORPORATE HSE POLICY DOCUMENT / HDEC 6.2 HSE HDEC THE HDEC CORPORATE HSE MANUAL / HSE 6.3 THE HDEC CORPORATE HSE PROCEDURES / HDEC HSE 6.4 ISO 14001 (ENVIRONMENTAL MANAGEMENT SYSTEM) STANDARDS SPECIFICATIONS 14001 ( / 6.5 ) EHS GUIDELINES FOR THERMAL POWER PLANTS(DEC 19,2008) AND IFC/WB PERFORMANCE STANDARDS ON SOCIAL AND ENVIRONMENTAL SUSTAINABILITY(APRIL 30,2006) / (19 HSE ., 2008) / 6.6 (30 EIA (AGREED WITH ADB, DEC 15,2009) / ( ., 2008) , 15 2009 ) 7. ANNEXES / 7.1 CERTIFICATE OF ISO 14001 / 7.2 CONTRACTOR HSE POLICY STATEMENT / 7.3 ENVIRONMENTAL MANAGEMENT PLAN CHART / 14001 51 HSE Environmental Management Plan Rev. C [ANNEX 7.1 CERTIFICATE OF ISO 14001 / 7.1 52 14001] Environmental Management Plan Rev. C [ANNEX 7.2 CONTRACTOR HSE POLICY STATEMENT / HSE] 53 7.2 Environmental Management Plan Rev. C 54 Environmental Management Plan Rev. C [ANNEX 7.3 ENVIRONMENTAL MANAGEMENT PLAN CHART / Aspect Management Informing 7.3 Mitigation Location HSE Training center a)Inform local residents schedule of the construction activities. b)Introduce types of emission and countermeasures. . Emegency ] Monitoring Officialy Responsible a)Contractor Frequency Yearly (if required) b)PMU ( ) HSE Project Site a)Compile and implement a emergency situation control plan. . b)Every six months has emergency drills. Observation of emergency a)Contractor Inspection of traffic conditions a)Contractor Observation use of sources a)Contractor Daily b)Subcontractor . c)Confirms the role of individual Traffic . a)All traffic signs, signals, and road markings must be obeyed. , . b)Authorzed transportation of equipments and materials entry to the site Project Site Daily b)Subcontractor c)Speed of transport vehicles should be strictly controlled in the access road to TPP Monitoring . a) Monthly monitoring of the following should take place: Fuel (m3) Electricity (KWh) Project Site 55 b)Subcontractor Monthly Environmental Management Plan Rev. C Air / Plan / Water (m3) a)Identify all possible air pollution sources related to construction activities Project Site Examination of air plan a)Contractor b)PMU In advance of construction activities a)Subcontractor Monthly b)Compile and implement a air control plan Exhaust fumes a)Regularly serviced and maintained to be in good condition vehicles and Equipment Maintenance Area Inspection of air emission b)Appropriate manager b)Forbid the burning of coal, waste, or wood on site Project Site , c)Reduce idle time of all vehicles Dust / Plan / a)Identify all possible dust pollution sources construction activities Observation of air polution related to Project Site Examination dust plan , a)Contractor b)PMU In advance of construction activities a)Contractor a) Daily b)Subcontractor b)Windy Days b)Compile and implement dust control plan Watering / Watering shall be implemented to control dust where Project Site : a)Working areas b)Exposed areas c)Active cuts excavation and fill sites 56 Observation of watering Environmental Management Plan Rev. C Watering / Watering shall be implemented to control dust when Project Site Observation of watering : a)Before and after operation a)Contractor b)Subcontractor During construction activity a)Contractor Daily b)Breaking of rock/concrete work / c)Drilling of rock work Site control a)Minimize size and duration of exposed areas a)Project Site Observation dust control b)Keep hauling roads in good condition b)Subcontractor . Material control Minimize size and duration of materials stockpiles b)Laydown . Material control Vehicle control a)Minimum practical height to limit the fugitive dust generation from unloading excavated materials , , Project Site . b)Cement debagging should take place in a sheltered area. Batching Plant area a)Limiting vehicle-entrained dust from unpaved roads , , b)Limiting vehicle speeds (20 km/h in Project Site) and Project Site road 57 Observation material storage a)Contractor Observation of work a)Contractor Daily b)Subcontractor Daily b)Subcontractor Observation of traffic condition a)Contractor b)Subcontractor Daily Environmental Management Plan Rev. C restricting traffic volumes c)Trucks have proper fitting side and tail boards d)Materials shall also be dampened, if necessary, before transportation , , e)Covering trucks during transport of materials Noise / Plan / a)Identify all possible noise pollution sources related to construction activities , Project Site Examination of noise plan a)Contractor b)PMU In advance of construction activities b)Compile and implement a noise control plan c)Posting Signboards on construction sites and/or stickers on equipment outlining how affected parties can lodge complaint / . Noise level a)Inspect noise level of the construction equipment Project Site Inspection of noise level a)Contractor b)Subcontractor b)Equipment Noise limit will comply with Item 223 of EIA. For example. Direction of Nuristan are limited to 80 dba 1m 58 During construction activity Environmental Management Plan Rev. C Vehicle control 223 . . 80 1 c)Use appropriate PPE (earplug, earmuff) if exceeds noise limits ( , ), a)Limiting vehicle speeds (20 km/h at Project Site ) Project Site road b)Restrict truck movements to day time and restrict truck movements to major transport routes Vehicle control Noise barrier . a)Regularly serviced and maintained to be in good condition vehicles and Equipment a)Use of temporary acoustic barriers or exhaust mufflers Maintenance area Project Site b)Noise barriers located between noisy construction activities and noise sensitive receivers , Observation of traffic control a)Contractor Inspection of repair records a)Subcontractor Observation use of noise protector. a)Contractor Observation a)Contractor Daily b)Subcontractor Monthly b)Appropriate manager Daily b)Subcontractor c)Noise maintained at 70 dB at outside of nearest building from power plant 70 Equipment a)Equipment shall be operated within specifications and capacity 59 Project Site Daily Environmental Management Plan Rev. C control work of equipment b)Subcontractor b)Equipment shall be operated in as diversified a manner as possible c)Equipment shall be turned off when not in use , d)Work using machines or vehicles shall be prohibited in the midnight and the dawn . e)Air intakes, vents, and stacks should be fitted with suitable noise attenuating equipment (if required) , Equipment control ( ) a)Select the time when the environment is least sensitive to noise impact using pile drivers, jack hammers, and rock drills , Project Site Inspection of noise level a)Contractor b)Subcontractor During construction activity , Wastewater / Plan / a)Identify all possible wastewater pollution sources related to construction activities , b)Compile and implement a wastewater control plan 60 Project Site Examination of wastewater plan a)Contractor b)PMU In advance of construction activities Environmental Management Plan Rev. C Batch plant control Washing water Washing water a)Wastewater from concrete batching plant operation and shall not be discharged overland , , Batching Plant area a)Undertake settling and neutralization of alkaline washing water containing excessive cement prior to discharge , , b)Water from washing large concrete-mixing equipment Batching Plant area a)All washing of equipment or machinery shall be undertaken in designated areas Washing area Observation of wastewater a)Contractor Observation of washing water a)Contractor b)Subcontractor Operation of batching plant Observation of washing area a)Contractor Daily Observation of wastewater a)Contractor Observation of natural water a)Contractor Observation a)Contractor b)Subcontractor Operation of batching plant b)Subcontractor b)Washing of equipment areas must be equipped with a suitable impermeable floor and sump/oil trap / Wastewater emission Natural water Rain water . a)Wastewater collected within bunded area around the fuelling area be disposed of as hazardous waste , , a)Natural run-off diverted away from any camps Fuelling area Camp area a)Heavy rain water plan to be and implemented for the 61 Project Daily b)Subcontractor Daily b)Subcontractor During Environmental Management Plan Rev. C construction phase of the Project Site of rain water Heavy rain b)Subcontractor Contaminate d water Material control . a)Sand, silt and silt-laden water do not enter the water drain system or KMC , , a)All hazardous material storage areas designed to reduce risk of spillages Project Site Observation of water system a)Contractor Material storage areas Observation of material storage condition a)Contractor Project Site Observation of strain a)Contractor During Heavy rain b)Subcontractor Daily b)Subcontractor b)All materials covered during transport to prevent them from spilling c)Store all liquid/solid waste properly above ground to avoid spills/leaks / / d)Develop a hazardous materials and handling plan .provide spill response kits at all HazMat storage areas and work site . . e) Chemicals and fuels on site should be kept to a minimum Straining a)Construct of dirt trap, interceptor pond and the attenuation dam(if required) commenced as early as possible in the 62 Weekly Environmental Management Plan Rev. C construction phase system. b)Subcontractor Project Site Experimentation of UG water a)Laboratory Monthly Project Site Observation of silt removal facilities a)Contractor Daily , ( Underground water ) . a)Monitoring the underground water by sampling of underground water at site around four(4) points 4 ( ) . b)The location will be qualified and used for periodic sampling. Barrier Hazardous waste Monitoring . a)Channels, earth bund walls or sandbag barriers be provided on site to direct rain water to silt removal facilities , b)Subcontractor Storage of hazardous waste in bunded areas to avoid leaks escaping to the ground or nearby surface waters , Hazardous waste bunded area Observation of harzardous waste a)Contractor a)Monitoring water quality Project Site Experimentat ion of wastewater a)Laboratory b)Water samples, sent to local laboratory to be tested for Water quality ph, oil, debris and etc , . . , , , 63 Weekly b)Subcontractor Monthly Environmental Management Plan Rev. C Soil / Plan / a)Identify all possible construction activities soil pollution sources related to Project Site Examination of soil plan. , a)Contractor b)PMU In advance of construction activities b)Compile and implement a soil control plan Site control a)Minimize size and duration of exposed areas Project Site b)Minimize the excavation during construction of fuel oil Observation of soil emission a)Contractor b)Subcontractor During construction activity Observation of silt and grit a)Contractor Monthly c) Minimize the overall slope of the site d)Ensure good landscaping and erosion control Site control a)Deposited silt and grit removed regularly and disposed of by spreading evenly over stable Project Site b)Subcontractor Covering a)Exposed slope surface shall be covered during the rainy day Project Site Observation of material store a)Contractor Observation of traffic a)Contractor During rainy day b)Subcontractor b)Open stockpiles of construction materials covered during rainy day Road control a)Trafficked areas and access roads protected by coarse stone ballast 64 Project Site road Monthly Environmental Management Plan Rev. C b)Subcontractor Sediment Drainage facilities Vehicle control a)Sediment tanks can be used for settling wastewater prior to disposal Project Site Inspection of sediment tank ability a)Contractor b)Subcontractor Install sediment tank Inspection for maintanance a)Contractor Monthly a)All drainage facilities, erosion and sediment control structures shall be regularly inspected and maintained , Project Site a)All vehicles and plant cleaned before leaving a construction site Exits of the project site gate Observation of traffic condition a)Contractor Project Site road Observation of traffic condition a)Contractor b)Subcontractor Daily b)Subcontractor b)Ensure no earth, mud, debris and the like is deposited by them on roads , , , c)Adequately designed and sited wheel washing bay shall be provided at site exits Road control a)All road works separated from surface waters b)All roads shall be properly sloped and have adequate culverts to manage runoff 65 b)Subcontractor Daily Environmental Management Plan Rev. C c)Earthworks to construct drainage ditches and to lay subsurface drainage conduits Excavated material a)Excavated materials possible to used reclamation fill Project Site Observation of excavated material a)Contractor Daily Project Site Observation spill a)Contractor Daily b)Surplus excavated materials quarry overburden, rock rejected for aggregate, aggregate surplus to the requirements and the like not discarded indiscriminately , , , , c)Different types of surplus excavated materials deposited separately in the spoil dumps designated for the purpose outside the Project site , Overall Spill Control Management a)Any spillage of fuel shall straight away be absorbed using sand or other absorbent materials b)Subcontractor . b)Develop spill response plan . c)Only people with adequate training and knowledge should handle fuel and chemicals to avoid spills 66 Examination of spill plan Observation Prior to fuel bulk storage Environmental Management Plan Rev. C of spilling , . Daily d) Fuelling should be one on concrete surface provided with spill catch tank that can be easily cleaned and all spilled fuel recovered/safety disposed , / e) All repair and maintenance work to be done either on concrete surface with oil spill catch basins or oil catch pans provided at all service areas , - f) Routinely inspect all equipment handling hazardous materials for leaks and spills g) All fuel where spills and leakage area possible e.g. the generator, must have basins installed to prevent leakage , , f) The recovered materials must be recycled h) Fuelling equipment must be fitted with proper fuel nozzles and devices to avoid accidental spills 67 Environmental Management Plan Rev. C Storing a)All fuel stored on site shall be kept in drums or in bulk tanks , , Fuel Storage area Observation of oil storage Project Site Observation of oily water a)Contractor Daily b)Subcontractor b)Fuel storage area be located at a designated place away from any source of ignition or open drain c)“No Smoking” sign displayed at the storage location and a charged fire extinguisher of the correct type « » . d)All fuel tanks and storage areas provided with concrete embankments to readily contain spills Oil emission Refueling e)provide spill kits at all working areas a)Treat oily wastewater in coalescence separator prior to discharge . Refuelling of vehicles shall take place only in designated areas . Training Fuel handling training shall include chemical handling in the 68 a)Contractor Daily b)Subcontractor Fuel Storage area Observation of refuelling Training Training of oil a)Contractor Daily b)Subcontractor Contractor As needed Environmental Management Plan Rev. C training program for assigned personnel. Center handling roject Site Examination of waste plan . Waste Plan / a)Identify all possible waste pollution sources b)PMU In advance of construction activities Observation of waste facility a)Contractor Weekly Observation of waste control a)Contractor b)Compile and implement a waste control plan a)Contractor c)Procedures detailed in the Material Safety Data Sheet (MSDS) for hazardous materials included in pollutants spillage control plan and followed in the event of an emergency situation , , Waste Disposal Waste disposal . a)Dispose unusable waste streams at permitted waste disposal facilities a)Separate waste disposal area shall be designated on the construction site b)Separate waste disposal area contains clearly demarcated skips and bins to allow different types of waste c) Waste is separated into non-hazardous and hazardous / potentially hazardous prior to reuse, recycling or transport to 69 Disposal facilities Disposal area b)Subcontractor b)Subcontractor c)disposal company Daily Environmental Management Plan Rev. C Landfill / , . d)Domestic, metal scrap, used oil, paper, hazardous etc. , , , , . . e) Disposal of all waste appropriately (with formal contracts with waste management companies) ( Waste disposal Hazardous waste ) a)The wide range of materials and chemicals involved such as oil, lubricants, cutting oils, sludge, paints etc. , , , , , . b)Hazardous waste shall be identified, classified, handled and disposed of safely , , Identify types of hazardous waste: a)Fuel, waste oil, paints and contaminated material with oil , , b)Sludge contaminated with heavy metals , c)Corrosives, including acids and alkalis , 70 Project Site Observation of waste Contractor Daily Project Site Examination of hazardous waste a)Contractor In advance of construction activities b)Subcontractor Environmental Management Plan Rev. C d)Other hazardous substances e)Appointment of approved contractor for the removal of hazardous and solid waste to existing incineration and landfill areas approved by Hokimiyat and SES , Reuse Project Site a)Re-use the waste during construction Observation of reuse waste. a)Contractor Project Site Observation of reuse material. Contractor Daily Out of the project site Training waste disposal a)Contractor Monthly b)Re-use or recycle waste streams to other users at other locations Reuse a)The design of formwork could maximize the use of standard wooden panels Daily b)Subcontractor b)Alternatives such as steel formwork or plastic facing could be considered to increase the potential for re-use , , Recycle Waste Rubbish bins a) Develop dedicated area for storage of recycled material away from active construction works and near site access point . a) Provide sufficient bins with lids to store the solid waste produced on a daily basis , . 71 Project Site of Observation of waste disposal b)Subcontractor a)Contractor b)Subcontractor Weekly Environmental Management Plan Rev. C b) Bins not allowed to become overfull and shall be emptied as a minimum on a weekly basis Rubbish bins Discharge . a)Implement adequate numbers of rubbish bins around construction site and in construction camps c)disposal company a)Project Site b)Install signage encouraging use of rubbish bins on site and in construction camps , b)Camp a)Prohibit dumping of dredge material in canal or elsewhere on site , Project Site Observation of waste disposal a)Contractor Daily b)Subcontractor c)disposal company Observation of dumping a)Contractor Daily b)Subcontractor Storing a)Design and implement a temporary waste storage area for domestic waste Project Site Observation of waste store area a)Contractor Observation of waste store area a)Contractor Daily b)Subcontractor b)Located away from living and eating areas c)Separation of storage of hazardous and non-hazardous waste storing Containers used for the storage of chemical wastes shall , , a)Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed , , 72 Storage area b)Subcontractor Daily Environmental Management Plan Rev. C , , b)Stored chemical in roofed areas with concrete flooring. . storing The storage area for chemical waste shall Project Site a) Be located away from surface water bodies. Observation of waste store area a)Contractor Daily Training waste disposal a)Contractor a)Monthly b)Subcontractor b)Random a)Contractor Daily b)Subcontractor b) Be constructed with a weatherproof cover, concrete floor with bunding, and with adequate securable storage bins for waste. , c) Have appropriate signage and signage system. . d) Be clearly labeled and used solely for the storage of chemical waste. e) Be enclosed on at least 3 sides. f) Be arranged such as to separate incompatible materials , Training Separating a)Include information on solid waste construction worker training program management in a)Wood and other scrap material with a commercial value shall be separated and stored in segregated areas prior to removal 73 Training center Project Site of Observation of waste control b)Subcontractor Environmental Management Plan Rev. C Battery a) The dead batteries will be given to specialized organizations for reuse Project Site Observation of battery a)Contractor Daily b)Subcontractor Chemical waste Disposal of chemical waste shall Project Site a)Treated by a licensed waste collector. Observation of chemical waste b)Be to a facility licensed to receive chemical waste, such as the chemical waste treatment , , a)Contractor Daily b)Subcontractor c)Waste collector c)Hazardous and toxic waste shall not be disposed of on the canal d)Hazardous waste shall be removed from the site property within 60 days. 60 e)Hazardous waste shall not be dumped onto the ground, into rain water sewers or into sanitary sewer system , Waste catering of a)Catering wastes is divided into food waste and non-food waste Catering Observation of catering a)Contractor b)Subcontractor b)All organic food waste generated by kitchen facilities to be disposed of at the landfill 74 c)Catering Daily Environmental Management Plan Rev. C , company c)Food waste daily removed from the kitchen d)Food waste always contained in plastic bags for disposal e)Non-food waste collected in separate beverage cans, packing materials, etc. containers as , Oily waste water , , . a)Oil and other lubricants collected in drums and disposed of in accordance with CONTRACTOR instructions 75 Project Site Observation of oily waste water. a)Contractor b)Subcontractor Daily